For Immediate Release
March 13, 2014
 
Work to build third lane of I-71 to restart
I-71 south reduced to two lanes starting tomorrow
 
FRIDAY, MARCH 14
Interstate 71 (NEW) Beginning at 7 a.m., I-71 south will be reduced to two lanes between SR 61 and US 36/SR 37 so crews can begin work on the northbound lanes of I-71.
 
Before work to build a third northbound lane can begin, ODOT must shift both directions of traffic over to the southbound lanes.  Two lanes will be maintained in each direction on I-71 for the duration of the project.
The first of three projects to widen 25 miles of I-71 in Delaware and Morrow Counties was completed last year between SR 95 and the Richland County Line. The other two projects are expected to be complete by Fall of this year.
 
For up-to-date traffic information, construction information and road conditions, 24-hours a day, visit www.Ohgo.com.
 
 
###