I-270 and US 33 Interchange Improvement
7/6/2017

Rain Impacts Paving on the Dublin Project

Due to the rain today and more in the forecast for tomorrow, here's an updated schedule for paving and concrete work on the I-270/US 33 project in Dublin. 

Thursday, July 6, 2017

  • 8 PM US 33 east reduced to two lanes between Avery-Muirfield Dr  and I-270.
  • 8 PM the ramp from Avery-Muirfield Dr. to US 33 east closed.  Detour: US 33 west to SR 161/Post Rd. to US 33 east.
  • 8 PM the ramp from US 33 east to I-270 east closed. Detour: I-270 south to Tuttle Crossing Blvd. to I-270 east/north.
  • 5 AM all lanes and ramps open

Friday, July 7, 2017

  • 9 AM US 33 east reduced to two lanes between I-270 and Frantz/Post Rd.
  • 3 PM all lanes open.

Friday, July 7, 2017

  • 8 PM US 33 east reduced to two lanes between SR 161/Post Rd. and Frantz/Post Rd.
  • 8 PM the ramp from US 33 east to I-270 south reduced to one lane.
  • 9 PM the ramp from I-270 south to US 33 east closed. Detour: I-270 south to Tuttle Crossing Blvd. to I-270 north to US 33 east.
  • 11 PM US 33 east thru lanes to Old Dublin closed and traffic forced to exit at I-270 south. Detour: I-270 south to Tuttle Crossing Blvd. to I-270 north to US 33 east.
  • 5 AM all lanes and ramps open.

Saturday, July 8, 2017

  • 8 AM US 33 east reduced to two lanes between I-270 and Frantz/Post Rd.
  • 3 PM all lanes open.

Sunday, July 9, 2017

  • 8 PM US 33 east reduced to two lanes between Avery-Muirfield Dr. and I-270.
  • 8 PM the ramp from US 33 to I-270 south closed. Detour: I-270 east to Sawmill Rd. to I-270 south.
  • 9 PM the ramp from I-270 north to US 33 east closed. Detour: I-270 north to Sawmill Rd. to I-270 west to US 33 east.
  • 5 AM all lanes and ramps open.

 

For more information contact: Nancy.Burton@dot.ohio.gov or call 740-833-8063.