I-270 and US 33 Interchange Improvement
3/20/2017
For Immediate Release
March 20, 2017
WORK TONIGHT (ONLY) CANCELLED DUE TO WEATHER
Overnight work a ‘go’ for the rest of the week
 
Tuesday, March 21, 2017 – I-270 SB Lane Closures for Bridge Work
  • 9pm I-270SB reduced to two lanes between Sawmill Rd. and US 33.
  • 11pm I-270SB reduced to one lane between Sawmill Rd. and US 33.
  • 5am all lanes open.
 
Wednesday, March 22, 2017 – I-270 SB Lane Closures for Bridge Work
  • 9pm I-270SB reduced to three lanes between Sawmill Rd. and US 33.
  • 5am all lanes open.
 
Thursday, March 23, 2017 – I-270 NB Lane Closures for Bridge Work
  • 9pm I-270NB reduced to two lanes between Tuttle Crossing Blvd. and US 33.
  • 5am all lanes open.
 
Friday, March 24, 2017 – I-270 NB Lane Closures for Bridge Work
  • 9pm I-270NB reduced to two lanes between Tuttle Crossing Blvd. and US 33.
  • 11pm I-270NB reduced to one lane between Tuttle Crossing Blvd. and US 33.
  • 5am all lanes open.