Modernization of I-75 through Downtown Dayton
I-75 and US 35 Downtown Dayton Phase 1B
Sale Date: Tentatively, December 2009
Estimated Start Date: Tentatively, January 2010
Estimated Completion Date: June 2013
Estimated Construction Cost: $58 million
Estimated Overall Cost: $71 million
Project Location: I-75 and US 35 interchange
Project Description: Modify the US 35 interchange to provide three continuous lanes in each direction on I-75. Close the southbound exit ramp to Albany St. Close the northbound entrance ramp from Albany St.
Project Benefits:
- Better traffic flow
- Three continuous lanes through Downtown Dayton