Start Date: Spring 2005
Completion Date: November 2009
Estimated Project Cost: $48.3 million
Project Location: I-70 from just west of the Dayton Airport Access Rd. to the CSX railroad east of I-75.
Project Description: Construct the remaining ramps. Construct new railroad bridge over I-70, just east of the interchange. Also landscape the infield areas.