BUTLER COUNTY
A project to replace a culvert will require a three-week closure
of State Route 126 beginning Monday, June 9.
The closure on SR 126 will be located between Chapel Road and
Alert New London Road in Morgan Twp. The suggested detour for westbound SR 126
is SR 748 to SR 129 to SR 126, and the reverse for eastbound SR 126.
SR 126 will reopen to traffic prior to the Fourth of July weekend.
On July 7, a second three-week closure of SR 126 will begin for culvert
replacement work between Morgan Ross Road and Layhigh Road in Ross Twp. with a
suggested detour for westbound SR 126 of SR 128 to U.S. 27 to SR 748 to SR 126,
and the reverse for eastbound SR 126.
GREENE COUNTY
As part of a
two-year project to resurface 5.5 miles of Interstate 675 in Greene
County, the ramp from southbound I-675 to Dayton-Yellow Springs Road will be
closed nightly this week from 9 p.m. to 6 a.m. The recommended detour is I-675
to the North Fairfield exit (#17) to northbound I-675 to Dayton-Yellow Springs
Road.
HAMILTON COUNTY
Work this week on the I-75/Hopple
interchange construction will require the following closures:
Double
left lane closure on northbound I-75 Tuesday, June 3 through Friday, June 6,
beginning at 10 p.m. and reopening to traffic by 6 a.m. the following day.
Closure will also include closure of the ramp from northbound I-75 to Hopple
Street. On
those days when a Reds game is scheduled,
the double lane closure will be permitted one hour after end of game. Ramp
closure is permitted between 10 p.m. and 5 a.m.
30-minute
closures of Central Parkway Tuesday, June 3 through Friday June 6, beginning at
10 p.m. and reopening to traffic by 5 a.m. the following day.
Lane
closures on Marshall Avenue from 9 a.m. to 3 p.m. each day.
30-minute
closures of Marshall Avenue Tuesday, June 3 through Thursday, June 5, beginning
at 10 p.m. and reopening to traffic by 5 a.m. the following day.
Closures
on various side streets from 9 a.m. to 3 p.m. each day.
All
work is weather permitting.
A single lane closure on north and southbound
Interstate 75 just south of State Route 562 beginning at 10 p.m., followed by a
double lane closure at midnight each night the week of June 2, with all lanes
opening to traffic by 6 a.m. the following day. Direction of lane closure and
configuration will be dependent on progress from previous night’s work