I-275/SR 32 Interchange Improvement update

I-275/SR 32 interchange improvement update
 
CLERMONT COUNTY  (Friday, March 28, 2014) – Work on the I-275 and SR 32 Interchange improvement project this week included the following:
 
·         The bridge deck and approach slabs on the northbound I-275 ramp to SR 32 were poured.
·         Traffic on the westbound SR 32 ramp to northbound I-275 has been adjusted, with the width of the ramp reduced to allow construction of temporary pavement.
·         Project personnel continue removing existing asphalt and are building the outside of east and westbound SR 32 from I-275 to Old SR 74.
·         Project-wide restriping of pavement was completed Thursday, March 27.
Work scheduled next week includes:
 
·         Lane closures on east and westbound SR 32 to remove bridge beams at the Eastgate Boulevard bridge.  Daily closures will be in place from 8 p.m. to 6 a.m.  Monday, March 31 and Tuesday, April 1, with 15-minute full closures scheduled between 10 p.m. and 6 a.m. 
·         The ramp from Eastgate Boulevard to westbound SR 32 will be closed from 8 p.m. Monday, March 31 to 6 a.m. the following day.  The ramp from eastbound SR 32 to Eastgate Boulevard will be closed from 8 p.m. Tuesday, April 1 to 6 a.m. the following day.
·         Median work on SR 32 continues from I-275 east to the Eastgate Boulevard overpass.