I-275/SR 32 interchange improvement update

I-275/SR 32 interchange improvement update
 
CLERMONT COUNTY  (Friday, March 14, 2014) – Work this week on the I-275 and SR 32 Interchange improvement project included the following:
 
Project personnel continue to monitor and adjust the timing of the I-275 exit ramps and SR 32 traffic signals to improve the flow of traffic in the area.
 
Work scheduled in the upcoming two weeks includes:
 
The bridge on the new northbound I-275 exit ramp over Aicholtz Road east of I-275 will be poured March 21.
 
Temporary pavement will begin being placed on the right shoulders of existing SR 32, beginning east of the eastern traffic signal (Station 90) to Eastgate Blvd., eastbound and westbound where needed.
 
Pavement removal will begin next week on the old ramps and portions of 32.