I-75 full closures scheduled week of Jan. 18

Full closure of Interstate 75 scheduled next week

Hamilton County (Thursday, Jan. 15, 2015) Bridge work will require nightly full closures of northbound Interstate 75 between the  Mitchell  Avenue and Norwood Lateral  interchanges beginning Tuesday, Jan. 20 and continuing through Saturday, Jan. 24.

The closure is scheduled from 11 p.m. to 5 a.m. each night, weather permitting. The detour is northbound I-75 to westbound I-74 to eastbound I-275 to northbound I-75.

In addition, work on southbound I-75 will require a single lane closure beginning at 8 p.m. followed by a double lane closure at 11 p.m. Monday, Jan. 19 and Wednesday, Jan. 21, with all lanes open to traffic by 6 a.m. the following day. Monday’s work includes closure of the ramp from SR 562 to southbound I-75 and a rolling road closure on southbound I-75. Work is weather permitting.

Also, work at the I-75/Hopple interchange will require the following closures the week of Jan. 18:

·    Double lane closure on southbound I-75 beginning 7 p.m. Sunday, Jan. 18 and 9 p.m. Monday, Jan. 19 through Thursday, Jan. 22, with all lanes reopen to traffic by 6 a.m. the following day. The lane closures will be in place from just north of I-74 to just south of Hopple. In addition, 30-minutes rolling closures will be in place on southbound I-75 from midnight to 5 a.m. each night.

·   Various lane closures on Marshall Avenue and side streets from 9 .m. to 3 p.m. each day.

Arrow boards and signs will be in place to alert motorists of the upcoming closures. To help ensure the safety of the construction workers as well as the traveling public, motorists should remain alert, reduce their speed and watch for stopped traffic while passing through the work zone.​