Sign In
An Official Site ofOhio.gov

I-75/Hopple construction update for week of May 5


 ​I-75/Hopple construction weekly update

Lebanon (Monday, May 5, 2014) – Work this week on the I-75/Hopple interchange construction will require the following closures:

·         Two right lanes of southbound I-75 from 10 p.m. to 6 a.m. Monday, May 5 through Friday, May 9. The ramp from southbound I-75 to Hopple Street will be closed each night from 10 p.m. to 5 a.m. each day, as well.

·         Two right lanes of northbound I-75 beginning at 10 p.m. Monday, May 5, and reopening by 6 a.m. Tuesday, May 6, with 30-minute rolling closures scheduled from midnight to 5 a.m.

·         Two left lanes of northbound I-75 beginning at 10 p.m. Tuesday, May 6, reopening to traffic by 6 a.m. Wednesday, May 7. The ramp from northbound I-75 to Hopple will be closed from 10 p.m. to 5 a.m., as well.

·         30-minute closures of Central Parkway on Thursday, May 8 from 10 p.m. to 5 a.m.

·          Lane closures on Marshall Avenue from 9 a.m. to 3 p.m. each day.

·         Right lane closure on northbound Central Parkway from 9 a.m. to 3 p.m. each day this week.

·         Right lane closure on southbound Central Parkway between the Connector Road and Marshall Avenue from 9 a.m. to 3 p.m. Monday, May 5 and Tuesday, May 6.

·         Implementation of a long-term (24 hours, seven days a week) right lane closure on southbound Central Parkway between the new Connector Road and Marshall Avenue Wednesday, May 7.

·          Closures on various side streets from 9 a.m. to 3 p.m. each day.

·         All work is weather permitting.​