Lane closures
scheduled for Interstate 75 bridge project
Hamilton County (Wednesday, Nov. 26, 2014 - The
railroad bridge replacement project on Interstate 75 south of SR 562 will
require various nightly lane closures on southbound I-75 next week.
Tuesday,
Dec. 2, Wednesday, Dec. 3 and Thursday, Dec. 4: Single
lane closure beginning at 8 p.m., followed by double lane closure at 11 p.m..
The ramp from SR 562 to southbound I-75 will close beginning at 9 p.m., with
all lanes reopened to traffic by 6 a.m. the following day. Also,
on Thursday, Dec. 4, a rolling road block will be in place on southbound I-75
to relocate a crane.
On Friday, Dec. 5, all lanes of southbound I-75 will be
closed between the SR 562 and Mitchell Avenue interchanges beginning at 11
p.m., with all lanes reopened to traffic by 8 a.m. Saturday, Dec. 6. The ramp
from westbound SR 562 to southbound I-75 will also be closed. Single lane
closures will be in place beginning at 9 p.m. Friday, Dec. 5.
Suggested detour is west on I-275 to east on I-74 to
I-75. The ramp from southbound I-75 to eastbound SR 562 will be open to traffic
as well.
All lanes of southbound I-75 will also be closed Monday,
Dec. 8, Tuesday, Dec. 9, and if necessary, Wednesday, Dec. 10, beginning at 11
p.m. with all lanes reopened to traffic by 6 a.m. the following day.
All work is dependent on the weather. Traffic will be
maintained with law enforcement officers, and arrow boards and signs will be in
place to alert motorists of the upcoming closure and detour.