Oxford’s U.S. 27 project begins work
Butler County (Tuesday, April 29, 2014) – Work to widen and perform other improvements to U.S. 27 in the city of Oxford is expected to begin this week.
This two-year project involves widening and resurfacing 1.05 miles of U.S. 27 between Southpointe Road and Chestnut Street; work will include adding turn lanes and upgrading traffic signals. This week, work will require a lane closure on U.S. 27 near its intersection with Chestnut Street on Thursday, May 1 and Friday, May 2 beginning at 7:30 a.m. Traffic will be maintained with a flagging operation. Traffic delays may be significant.
The Eagle Bridge Co. was awarded the contract on its bid of $7,566,360.