I-75 Brent Spence Bridge Maintenance

PID 97973

Rehabilitate the bridges and road involving the Ohio portion of the Brent Spence Bridge corridor that includes pier, wearing surface, joint, and drainage repairs, and zone painting.
  • Began: December 2015 – Estimated completion: summer 2017.
  • Cost: $9 million.

Current Status

  • Ongoing lane restrictions on Pete Rose Way. Nightly lane closures on I-71/I-75 are expected begin the week of April 24.

 

For information involving the Kentucky Transportation Cabinent maintenance project on the Brent Spence Bridge click: http://brentspence2017.org/

 

If you have questions or comments please send a email to: info@brentspence2017.org

 

 