 I-74 North Bend Bridge Replacement Ham-74-14.42 PID 93079

 
 

 Project will:

 
  • ​Construct new bridge with wider sidewalks;
  • Reduce congestion and improve safety with extended ramp deceleration lane across the
    bridge;
  • Provide improved route toward Cincinnati for oversized loads;
  • Repair pavement and resurface I-74;
  • Stabilize slope.
 

 ​Construction Info:

 
  • Project awarded to Sunesis Construction Co.
  • $8.203 million contract
  • Construction to begin Spring 2016
  • Phase 1: Late Spring through Fall 2016
  • Phase 2: Winter 2016 through Summer 2017
  • Completion August 2017
 