ODOT DISTRICT 10 ROAD CLOSURES/RESTRICTIONS
The following roads are either closed or restricted as of Monday, November 25, 2019. Click on each route to see the location at
OHGO.com.
ATHENS COUNTY
- SR-690 - Reduced to one lane just south of SR 550 due to a slip. Estimated end date is 12/1/19.
HOCKING COUNTY
- SR-78 - The route is closed just east of the intersection with SR-216 within the Murray City corporation limits due to a sewer replacement project. The work is scheduled for completion on 11/29/2019.
MEIGS COUNTY
SR-124 - The route is closed for the installation of a box culvert between Forked Run State Park and Curtis Hollow Road. A signed detour is set up using SR-248, SR-7, and SR-681. Work is scheduled for completion on 11/29/19.
MONROE COUNTY
SR-255 - A resurfacing project is taking place 0.47 miles west of CR-43. Flaggers and a 10 foot width restriction are in place. Work is scheduled for completion on 6/30/20.
SR-255 - The route is reduced to one lane 0.14 miles east of CR-98. Work is scheduled for completion on 12/31/19.
SR-255 - A slip repair project has the route reduced to one lane 1.08 miles west of SR-7. Traffic is maintained with temporary traffic signals. Work is scheduled to be complete on 11/30/19.
SR-255 - The route is being realigned at the 15.61 mile marker, just south of CR-96 (Baptist Ridge Road). One lane of traffic will be maintained with a temporary traffic signal. Work is scheduled to be completed on 11/30/19.
SR-536 - An emergency slip repair has the route restricted to a single lane between TR-437 and SR-7. Traffic is maintained with temporary traffic signals. Work is expected to be complete on 12/31/19.
SR-536 - An emergency slip repair has the route restricted to a single lane 5.95 miles north of SR-7. Traffic is maintained with temporary traffic signals. Work is scheduled for completion on 12/31/19.
SR-536 - A slip repair has the route reduced to a single lane at the 1.7 mile marker, approximately 0.75 miles north of CR-22. Traffic is maintained with temporary signals and a 12' width restriction is in place. Work is scheduled for completion on 12/31/19.
MORGAN COUNTY
SR-37 - Construction of roundabouts has the route restricted at
at the intersections of SR-37/SR-78/SR-669 and SR-37/SR-78/SR-60. Work is scheduled for completion on 12/13/19.
SR-78 - A culvert replacement project has the route reduced to a single 10' lane just west of McConnelsville. Work is scheduled for completion on 11/30/19.
SR-376 - A landslide has the route closed between Cottonwood Drive and Fairgrounds Road
- SR-376 - An emergency slip repair has the route restricted between McConnelsville and the Muskingum County line. Traffic is maintained with temporary traffic signals. Work is scheduled for completion on 12/31/19.
WASHINGTON COUNTY
- SR-26 - A landslide repair at the 28.96 mile marker has the route reduced to a single lane just north of TR-516. Work is scheduled for completion on 12/31/19.
- SR-550 - Crews will install a pre-cast concrete box culvert at MM 20, about 1.8 miles west of Marietta. Traffic will be maintained in one lane with a 12' width restriction. Work is scheduled for completion on 11/30/19.
- SR-555 - A landslide repair has the route reduced to a single lane at the 5.5 mile marker. Traffic is maintained with a temporary traffic signal. Work is scheduled for completion on 11/27/19.
- SR-676 - A landslide repair has the route reduced to a single lane at the 3.33 mile marker. Traffic is maintained with a temporary traffic signal. Work is scheduled for completion on 12/31/19.
- SR-676 - A waterline replacement project is taking place from the intersection of Alta St. & Riley Dr., to Alta St. and SR 676, and continuing down SR 676 to the intersection of SR 676 and SR 7. SR 676 will be closed from Alta Street to SR 7. Work is scheduled for completion on 12/31/19.