State Route 7 Widening Project from Marietta to Reno
Reduced speed limit to 35 MPH beginning at the SR 7 and Sandhill Rd intersection
Update - April 2010
Beginning May 2010, crews will be milling and paving from Sandhill Rd out to the Dimex building. Crews wil also be laying down the final seeding in the next few weeks. And finally, valve boxes and portions of new sidewalk will be installed. Traveling south from Reno to Marietta, a portion of the left lane is restricted to allow for valve boxes to be replaced.
Update - Wednesday, September 9
NEW - Check out the new SR 7 video featuring Project Engineer, Zach Bazell discussing the new project timeline and what motorists can expect during the final phases of the project.
SR 7 Project Update News Release
Project Overview: Project includes major widening and expansion of a portion of SR 7 through Marietta and Reno.
Project Cost: $14,580, 635
Construction Company: Shelly & Sands
Project Bid Date: 9/19/2007
Project End Date: Extended to end of July 2010