Additional Lane Opened on State Route 2 Eastbound over I-90

Garfield Heights (Friday, July 30, 2010) Overnight last night, Thursday, July 29, the Ohio Department of Transportation (ODOT) and Terrace Construction Company, Inc. opened one additional lane in the eastbound direction on the State Route 2 bridge over Interstate 90 in the city of Cleveland. 

Currently, two lanes in the eastbound direction and one lane in the westbound direction on State Route 2 over the I-90 Innerbelt Curve are open. One lane remains closed in each direction until mid-September. 

Intermittent, nightly lane closures on Interstate 90 beneath the structure are also expected during portions of the project.   

Crews will work both daily and nightly, 7 a.m. to 3:30 p.m. and 11 p.m. to 7 a.m., as the project progresses. 

The entire project replaces the deck of the State Route 2 bridge over Interstate 90 and is expected to be complete on, or around, August 30, 2010.

All dates and times are approximate and weather dependent.  For statewide construction and road condition information visit www.BuckeyeTraffic.org. 

Project Facts: 

Project:  Replace the deck of the State Route 2 bridge over Interstate 90 including approach slabs and minimal approach work.

Contractor: Terrace Construction Company, Inc. 

Bid Amount:  $1,208,754.64

Completion Date: August 30, 2010 

###

For more information contact:
The ODOT District 12 Communications Office at (216) 584-2006