I-480 Cloverleaf work to resume overnight April 11

Independence

April 10, 2008, Garfield Heights, OHWork to completely rehabilitate and rebuild the eastbound lanes of I-480 between Tuxedo Ave. and the Valley View Bridge will begin overnight Friday, April 11, 2008.

 

On Friday, April 11, crews will begin lane closures of I-480 eastbound at approximately 8 p.m. followed by the complete closure of the SR 176 (Jennings Freeway) southbound ramp to I-480 eastbound and Granger Rd./Brookpark Rd. entrance to I-480 eastbound at 10 p.m.  All lanes and ramps are expected to reopen by mid-morning Saturday, April 12.

 

Crews will work to shift eastbound traffic toward the center median maintaining three, reduced-width lanes during peak hours.  All lanes and ramps are expected to remain open during peak hours as the project progresses.

 

One lane of the SR 176 southbound ramp to I-480 eastbound will remain closed permanently in order to eliminate a tight merge and allow for smoother traffic flow onto I-480 eastbound.

 

All dates and times are approximate and weather dependent.  Should weather prohibit the operation overnight April 11, crews will move the operation to overnight Saturday, April 12.

 

Project Facts

Project:                    Major rehabilitation of  2.58 miles of existing mainline I-480 from Tuxedo Ave. to the Valley View Bridge, including inner and outer lanes and 3.8 miles of the I-77 and Granger Rd. interchange ramps.

Contractor:               Kenmore Construction Company, Inc.

Bid Amount:            $30,870,223.77

Completion Date:     November 2008

 

For statewide construction and road condition information visit us on the Web at www.buckeyetraffic.org.

###

FOR MORE INFORMATION CONTACT THE ODOT DISTRICT 12 PUBLIC INFORMATION OFFICE:

Jocelynn Clemings 216.584.2006 or Faye Callahan 216.584.2005

Ted Strickland, Governor             James G. Beasley, P.E., P.S., ODOT Director      Bonita G Teeuwen P.E., ODOT District 12 Director