This rendering shows the pair of new bridges upon completion in late 2016.
Regional Interstate Impacts: Overnight Fri, July 25, crews will close the ramp from I-90 west to I-77 south from 8 p.m. to 6 a.m. Sat morning. Motorists will be detoured via I-90 west to I-71 south to SR 176 south to I-480 east.
Downtown Impacts:
· Each night Mon thru Thurs, July 28-31, crews will close Ontario St under I-90 from approximately 7 p.m. to 6 a.m. each morning to remove steel overhead. Closure times will be adjusted to minimize impacts to downtown event traffic. Detour via E 9th St. Additional nighttime lane closures are anticipated, details will be forthcoming.
· During the week of July 28, work to widen Orange Ave and East 30th St will continue with daily lane closures.
Tremont Impacts: Be alert for construction vehicles crossing over Abbey and Fairfield Avenues. Flaggers will stop traffic temporarily while vehicles cross.
**Please note: Pile driving operations are expected to take place at various locations throughout the project site including near W 3rd St in the Flats and near Ontario St downtown. This operation is permitted to take place from 6 a.m. to 11 p.m., 7-days-a-week, however the contractor expects to work daylight/weekday hours only. |