  • This weekend, E 9th Street will be closed under I-90 for demolition of the bridge above. E 9th Street will remain closed from 7:30 p.m. on Friday, June 24 until 6 a.m. on Monday, June 27. Traffic will be detoured via Carnegie and Ontario. Along with this work, the I-90 eastbound ramp to E 9th Street and E 9th Street ramp to I-77 southbound will also be closed. Motorists will be detoured via Broadway/Ontario. The E 9th Street ramp to I-90 westbound will remain open.
  • Monday through Friday, June 27 to July 1, E 9th street will have lane closures in each direction from 9 a.m. to 3:30 p.m.
  • Monday through Friday, June 27 to July 1, crews will be paving southbound Broadway from E 14th St to the I-77 entrance ramp, south of I-490. Paving hours are not yet determined. This report will be updated on Monday with scheduled paving times.
  • Daily and nightly lane closures on Orange Avenue between E 9th and E 30th Streets will take place through early July as crews work to widen the roadway.
  • I-90 lane closures will take place during off-peak hours.
  • Both daily and nightly lane closures on E 14th Street under I-90 continue through early summer.
  • Daily lane closures are expected on the E 14th Street exit ramp from I-90 as well as on the extension of Community College Avenue in the vicinity of St. Vincent Charity Hospital.
  • I-90 westbound restrictions to two (2) lanes between E 14th Street and Ontario Street will be delayed until the eastbound restrictions are put in place after July 4. Motorists should still Opt for the Alternate! and use I-490 and I-77 to avoid downtown congestion.

Regional Interstate Ramp Impacts

  • Overnight Monday and Tuesday, June 27-28, crews will be paving the ramp from I-490 east to I-77 south, from 7 p.m. to 6 a.m. Motorists may encounter brief delays.
  • Overnight Friday, June 24 crews will close the I-77 northbound ramp to I-90 eastbound from 7:30 p.m. until 6 a.m. to pour a portion of new concrete bridge deck. Motorists will be detoured via the E 9th Street ramp to E 14th Street to Broadway/Ontario Street northbound to Superior Avenue eastbound to reenter I-90 eastbound.

Tremont Impacts

  • On Monday, June 27, I-71 southbound will have a lane closure from Kenilworth to beyond Starkweather, from 9 a.m. until 1 p.m.
  • Crews work to widen the I-71 southbound bridge over Starkweather. Minor lane restrictions and sidewalk closures will continue through the fall of 2011.
  • Until approximately July 20, crews on behalf of the Northeast Ohio Regional Sewer District work to relocate an existing sewer in Cleveland's Tremont neighborhood. Work is nearly complete, however minor operations remain. For more information, please contact NEORSD at 216.881.6600.

Permanent or Long-Term Closures and Construction Operations

  • Pile driving operations will continue through the fall of 2011.
  • Motorists may no longer access E 22nd Street from I-90 eastbound through the 2011 construction season. I-90 motorists should use Broadway Avenue to access E 22nd Street. I-77 northbound motorists may still access E 22nd Street.
  • The I-90 westbound ramp to I-77 southbound and I-77 northbound ramp to I-90 eastbound are restricted until approximately mid- to late June 2011.
  • The E 21st Street ramp to I-77 southbound is closed through approximately 2016.
  • The I-90 eastbound ramp to I-77 southbound and I-77 northbound ramp to I-90 westbound are permanently closed and motorists are rerouted via I-490.
  • University Road is permanently closed between W 13th Street and Scranton Road.

Please exercise caution in work zones. For statewide construction information visit: www.BuckeyeTraffic.org
Motorists are encouraged to ride
RTA or carpool through OhioRideshare during these restrictions.
To unsubscribe from this group, please reply with "Unsubscribe" in the subject line.
For more information, log-on to
Innerbelt.org or dial the Project Hotline at 216.344.0069.