Innerbelt e-mails include traffic operations which are new or different for the week. For a complete list of long-term & permanent closures and operations - including a map of recent & upcoming changes - please log-on to www.Innerbelt.org and click on "Traffic Impacts." Remember... Opt for the Alternate! and use I-490 and I-77 to avoid downtown construction.

Gateway Impacts

  • Monday, August 15, through Friday, August 19, motorists should expect lane closures on E 9th Street and E 14th Street from 9 a.m. to 3 p.m.
  • Starting Monday, August 15, for approximately two weeks, crews will be conducting paving operations on Broadway Avenue, between Orange Avenue and I-77 (south of I-490). During that paving, Broadway Avenue will have various lane restrictions. Northbound paving will generally happen between 9 a.m. and 6 a.m. the following morning. Southbound paving will be scheduled for 6 p.m. until 3 p.m. the next afternoon. These hours will be adjusted to provide unrestricted access to/from scheduled events.
  • NEW! Wednesday, August 17, E 14th Street will be closed under I-90 from 8 p.m. Wednesday night to 6 a.m. Thursday morning, for painting.
  • Friday, August 19 at 8 p.m. through Monday, August 22, at 6 a.m., I-90 west will be closed between I-77 and Ontario as crews shift traffic in the area. Westbound I-90 traffic will be detoured via I-77 south to I-490 west. The closure is necessary as crew move westbound traffic onto the newly completed pavement and create a new work zone in the middle, between the east and westbound traffic lanes. Upon completion of the traffic shift on Monday morning, westbound traffic will no longer be maintained using the "cattle-chute" configuration. I-90 traffic will still be restricted to two lanes in each direction and associated closures and restrictions will remain in effect.

Regional Interstate Ramp Impacts

  • On Saturday, August 13, the ramp from I-90 west to I-77 south will have a lane restriction from 6 a.m. to 5 p.m.
  • Monday, August 15, through Friday, August 19, the ramp from I-90 west to I-77 south will have a lane restriction from 9 a.m. to 3 p.m.

Closure dates/times may change based on special events and work conditions. Please visit www.Innerbelt.org for the latest information.

Cleveland Street Closures for The Avengers**

  • UPDATED! Beginning Monday, August 15 and continuing through August 24, Euclid Avenue will be closed between E 6th and E 12th Streets. Signage will be posted for alternate routes on E 6th Street, Superior Avenue, East 18th Street and Carnegie Avenue.
  • Beginning Wednesday, August 17 and continuing through August 30, South Roadway (the southwest corner of Public Square) will be closed between Superior Avenue and Ontario Street. Signage will be posted for alternate routes on Ontario Street and Superior Avenue.
  • Entire intersections will also be closed during the week. Go to http://webapp.cleveland-oh.gov/aspnet/moc/The Avengers Film Production Closures and Alternate Routes 1.pdf for the most recent closure schedule.

**Filming schedule and closures are subject to change. For more information, log-on to www.city.cleveland.oh.us and select "Press Releases."

Please exercise caution in work zones. For statewide construction information visit: www.BuckeyeTraffic.org
Motorists are encouraged to ride
RTA or carpool through OhioRideshare during these restrictions.
To unsubscribe from this group, please reply with "Unsubscribe" in the subject line.
For more information, log-on to
Innerbelt.org or dial the Project Hotline at 216.344.0069.