Gateway Impacts

  • Overnight Wednesday, May 18 crews will close E 14th Street under I-90 from 8 p.m. until 6 a.m. Motorists will be detoured via E 9th or E 22nd Streets.
  • Nightly lane closures on I-90 over E 14th Street will continue.
  • Daily lane closures are expected on the extension of Community College Avenue in the vicinity of St. Vincent Charity Hospital.
  • Both daily and nightly lane closures on E 14th Street under I-90 continue through early summer.
  • The planned work on E 22nd Street, between Carnegie and Cedar, has been temporarily delayed. An unanticipated utility conflict must be resolved before the work can begin. Work should resume within the next two weeks.

Regional Interstate Ramp Impacts

  • Overnight Tuesday, May 17 crews will restrict traffic on the ramp from I-77 southbound to I-490 westbound from 7 p.m. until 6 a.m. for asphalt paving. Motorists should expect brief delays during this time.
  • Overnight Wednesday, May 18 crews will restrict traffic on the ramp from I-490 eastbound to I-77 northbound from 7 p.m. until 6 a.m. for asphalt paving. Motorists should expect brief delays during this time.
  • Overnight Thursday, May 19 crews will restrict traffic on the ramp (near W 25th Street) that carries I-90 eastbound over I-490 eastbound and that connects to I-71 southbound, from 7 p.m. until 6 a.m. for asphalt paving. Motorists should expect brief delays during this time. One lane of I-90 eastbound will also be closed approaching this general vicinity during the paving.
  • Overnight Thursday, May 19 crews will close one lane of I-90 westbound approaching the I-77 southbound ramp, from 7 p.m. to 6 a.m. Crews will be modifying the ramp from I-90 westbound to I-77 southbound.

Asphalt paving operations are weather-dependent and may be rescheduled, if needed.

Tremont Impacts
Crews on behalf of the Northeast Ohio Regional Sewer District work to relocate an existing sewer in Cleveland's Tremont neighborhood.

  • Abbey Avenue is closed between W 12th Street and W 13th Street until Summer 2011.
  • W 11th Street is closed between University Road and Abbey Avenue until Summer 2011.
  • W 14th Street, just south of Fairfield Avenue, has lane restrictions until mid-May 2011.

For more information, please contact NEORSD at 216.881.6600.

Permanent or Long-Term Closures and Construction Operations

  • Pile driving operations will continue through the fall of 2011.
  • The I-90 westbound ramp to I-77 southbound and I-77 northbound ramp to I-90 eastbound are restricted until approximately late May 2011.
  • The E 21st Street ramp to I-77 southbound is closed through approximately 2016.
  • The I-90 eastbound ramp to I-77 southbound and I-77 northbound ramp to I-90 westbound are permanently closed and motorists are rerouted via I-490.
  • University Road is permanently closed between W 13th Street and Scranton Road.

Please exercise caution in work zones. For statewide construction information visit: www.BuckeyeTraffic.org
To unsubscribe from this group, please reply with "Unsubscribe" in the subject line.
For more information, log-on to
Innerbelt.org or dial the Project Hotline at 216.344.0069.