Only minor operations will take place next week as part of the Innerbelt Bridge project.  Details are below:
·        Monday through Saturday, December 3-8, one of the Tremont I-90 underpasses is likely to be closed each day, as a variety of work continues. Signage will be clearly posted indicating which street is closed each day.
·        On Monday, December 3, crews will return to install fence along the north side of the Abbey Avenue bridge. Motorists should be alert for flagging operations around the work crew and be prepared to stop briefly.
·        NEW!!  Beginning Thursday, December 6, the Carnegie leg of the entrance ramp from E 9th Street to I-90 west will be closed. Traffic still has access to the entrance ramp from E 9th Street. This leg of the ramp will remain closed until approximately December 31.
Join the Conversation!  Tremont West Development Corporation and the Innerbelt Bridge Project Team invite you to learn more about the Innerbelt Bridge project and get the latest update on project progress by participating in our final "Construction Conversation" of 2012.  Join us on Wednesday, December 5 from 5:30-6:30 p.m. at Sokolowski's University Inn.  We hope to see you there!
Please exercise caution in work zones. For statewide construction information visit: www.BuckeyeTraffic.org.  Motorists are encouraged to ride RTA or carpool through OhioRideshare during these restrictions.  To unsubscribe from this group, please reply with "Unsubscribe" in the subject line.  For more information, log-on to Innerbelt.org or dial the Project Hotline at 216.344.0069.