Ohio.gov State Agencies  |  Online Services
Skip Ribbon Commands
Skip to main content
Navigate Up
Sign In
 

 

U.S. 20 resurfacing to begin overnight Sunday, August 10

Mentor

 

August 8, 2008, Garfield Heights, OH Beginning at approximately 7 p.m. on Sunday, August 10 crews will begin a project to resurface U.S. 20 (Mentor Avenue) between the western Mentor corporation line and Hopkins Road in the city of Mentor.

 

Crews will work nightly, Sunday through Thursday between approximately 7 p.m. and 6 a.m. each morning.

 

Work will begin between Hopkins Road and State Route 615.  Traffic will be maintained with one lane in each direction during all working hours.

 

The entire project is expected to be complete by August 31, 2009.

 

All dates and times are approximate and weather dependent.

 

Project Facts

Project:                    Draining, planning and resurfacing with asphalt concrete.

Contractor:               Burton Scot

Bid Amount:            $2,707,000.00

Completion Date:     August 31, 2009

 

For statewide construction and road condition information log-on to www.BuckeyeTraffic.org.

###

FOR MORE INFORMATION CONTACT THE ODOT DISTRICT 12 PUBLIC INFORMATION OFFICE:

Jocelynn Clemings 216.584.2006 or Faye Callahan 216.584.2005

Ted Strickland, Governor             James G. Beasley, P.E., P.S., ODOT Director      Bonita G Teeuwen P.E., ODOT District 12 Director