February 20, 2009, Garfield Heights, OH In addition to permanent work zones and daily work plan, the following work is scheduled to take place over the weekend in Cuyahoga and Lake Counties:

Saturday, February 21:
I-90 Bridge Survey Work, Leroy Township, Lake County
On Saturday, February 21 crews will close one lane in each direction on the I-90 east and westbound bridges over Paine Creek from 8 a.m. to 2 p.m. in order to perform survey work.

Sunday, February 22:
I-71 Waterline Work, Strongsville, Cuyahoga County
Beginning Sunday, February 22 and continuing week nights though approximately March 13, crews will close the right two lanes of the I-71 southbound ramp to State Route 82 westbound from 8 p.m. until 6 a.m. each morning.  One lane will remain open for access.  Work is necessary as City of Strongsville crews perform waterline work in the vicinity.

All dates and times are approximate and weather dependent.

ODOT: “Moving Ohio into a Prosperous New World” 

###

FOR MORE INFORMATION CONTACT THE ODOT DISTRICT 12 PUBLIC INFORMATION OFFICE:

Jocelynn Clemings 216.584.2006, Faye Callahan 216.584.2005 or Mark Ziaja 216.584.2007

Ted Strickland, Governor             Jolene M. Molitoris, ODOT Director            Bonita G Teeuwen P.E., ODOT District 12 Director