Northeast Ohio
State
Route 2, Lake County
Rehabilitation of SR 2 between the Cuyahoga County
line and SR 91. Crews will work in the eastbound
direction between the Cuyahoga County line and E.
305th St., and in the westbound direction between SR
91 and E. 305th St.
Three lanes of
traffic in each direction are maintained during peak
hours. Single and double lane closures are expected
during off-peak hours Friday, May 25.
However,
While the permanent work zone remains in
place, crews will not be active between Saturday,
May 26 and Monday, May 28 and there will be no
additional lane closures during these days.
Completion date: October 2008.
State
Route 2, Erie County
SR 2,
between SR 13 and Berlin Rd., is reduced to one lane
of traffic in each direction as part of a
resurfacing project.
While the permanent
work zone restrictions remain in place, work is
suspended over the weekend and there will be no
additional lane closures.
Completion date: July 31, 2007.
State
Route 8, Summit County
The
reconstruction of SR 8 from south of Twinsburg Rd.
to north of the I-271 interchange. Two lanes of
traffic in each direction will be maintained on SR 8
at all times. Twinsburg Rd. at SR 8 is closed, and
will reopen with SR 8 as an overpass in late fall
2009. While
the permanent work zone restrictions remain in
place, work is suspended over the weekend and there
will be no additional lane closures.
Detours are posted. Completion date: summer
2010.
State
Route 11, Mahoning County
SR 11
between US 224 and I-680 is reduced to one lane in
each direction for roadway construction. The work
will also occur during the evening and overnight
hours, and motorists should be cautious while
traveling through at these times. Completion date:
November 2007.
State
Route 11, Trumbull County
SR 11
northbound, from SR 305 to the Ashtabula County line
is reduced to one lane traffic for paving. The
southbound lanes are unaffected.
While the permanent
work zone restrictions remain in place, work is
suspended over the weekend and there will be no
additional lane closures.
Completion date: November 2007.
State
Route 13, Richland County
SR 13,
near the northern corporation limits of the Village
of Bellville, is restricted to one-lane of two-way
traffic using flaggers as part of a resurfacing
project. Completion date: July 31, 2007.
State
Route 18, Medina County
Two separate sections of SR 18, between Windfall Rd.
and Beach Rd., and between Bambeck Rd. and the
Medina/Summit County line, are reduced to one lane
of traffic in each direction as part of a widening
and reconstruction project.
While the permanent
work zone restrictions remain in place, work is
suspended over the weekend and there will be no
additional lane closures.
Completion date: June 2008.
State
Route 18, Medina County
SR 18,
between Foote Rd. and Victor Rd., is restricted to
one lane of traffic in each direction during daytime
hours for a bridge replacement project. Between 7:00
p.m. and 5:00 a.m. each night, one lane of two-way
traffic will be maintained at all times. Completion
date: Oct. 15, 2007.
U.S.
Route 20, Lake County
Widening and reconstruction project on U.S. 20 from
the Mentor corporation line to Fern Dr. One lane of
traffic in each direction is maintained on U.S. 20
at all times. Palmer Ave. is closed between Jackson
St. and U.S. 20, and restricted to local access
only. While
the permanent work zone remains in place, crews will
not be active between Saturday, May 26 and Monday,
May 28 and there will be no additional lane closures
on these days.
Detours are posted. Completion date: August 2008.
U.S. Route 20, Lake County
Resurfacing project on U.S. 20 between the Chagrin
River and western Mentor corporation line. Traffic
is maintained with one lane in each direction. While
the permanent work zone remains in place, crews will
not be active between Saturday, May 26 and Monday,
May 28 and there will be no additional lane closures
on these days. Pelton Rd. between Mentor Ave. and
Kirtland Rd. is closed permanently. Detour is
posted. Completion date: August 2007.
State Route 58, Ashland County
Resurfacing on SR 58, between the city of Ashland
and SR 89. SR 58 is restricted to one-lane of
two-way traffic using flaggers during work hours
until 7 p.m. Thursday, May 24. Work is suspended
over the weekend and there will be no additional
lane closures until 6 a.m. Tuesday, May 29.
Completion date: Aug. 31, 2007.
State Route 60, Erie County
Resurfacing on SR 60, between the city of Vermilion
and SR 113. SR 60 is restricted to one lane of
two-way traffic using flaggers during work hours
until 7 p.m. Thursday, May 24. Work is suspended
over the weekend and there will be no additional
lane closures until 6 a.m. Tuesday, May 29.
Completion date: July 15, 2007.
Interstate 71, Medina County
Major reconstruction and widening of I-71, from
one-half mile north of Leroy Rd. to three-quarters
of a mile south of SR 3. Two lanes of traffic are
being maintained in each direction. Completion date:
summer 2010.
Interstate 71, Medina County
Major reconstruction and widening of I-71 from SR 18
to I-76. Two lanes of traffic are being maintained
in each direction. While the permanent work zone
restrictions remain in place, work is suspended over
the weekend and there will be no additional lane
closures. Completion date: Sept. 30, 2007.
Interstate 71, Medina County
Major reconstruction and widening of I-71 from one
mile south of U.S. 224/I-76 to the Wayne County
line. Two lanes of traffic are being maintained in
each direction. While the permanent work zone
restrictions remain in place, work is suspended over
the weekend and there will be no additional lane
closures. Completion date: June 10, 2007.
Interstate 76, Medina County
Major reconstruction and modifications to the I-76
and I-71 interchange. Two lanes of traffic are being
maintained in each direction. While the permanent
work zone restrictions remain in place, work is
suspended over the weekend and there will be no
additional lane closures. Completion date: summer
2010.
Interstate 77, Cuyahoga County
Replacement of the deck of the I-77 bridge over
I-480. Two lanes of traffic are maintained in each
direction. While the permanent work zone remain in
place, crews will not be active between Saturday,
May 26 and Monday, May 28 and there will be no
additional lane closures on these days. Completion
date: October 2008.
Interstate 77/Shuffel Road, Stark County
Shuffel Rd. over I-77 is closed for the construction
of a new interchange with I-77 in Jackson Township.
Frank Ave., between Strausser St. and the existing
Shuffel Dr. is closed. Waywood St. at Frank Ave. is
closed. At least two lanes of traffic will be
maintained in each direction on I-77. While the
permanent work zone restrictions remain in place,
work is suspended over the weekend, and there will
be no additional lane closures.Detours are posted.
Completion date: Oct. 30, 2007.
Interstate 77, Stark County
Widening and reconstruction on I-77 from W.
Tuscarawas St. (SR 172) to 13th St. Two lanes of
traffic are maintained in each direction on I-77.
The following are closed:
-
The 4th St. bridge over I-77;
-
Both I-77 northbound entrance ramps from
Tuscarawas St. The I-77 ramps are to remain closed
until November 2007;
-
13th St. under I-77 has various lane restrictions
in either or both directions until November 2007;
and
-
Tuscarawas St., from I-77 to Schroyer Ave., is
reduced to one lane in each direction until fall
2007.
While the permanent work zone restrictions remain
in place, work is suspended over the weekend and
there will be no additional lane closures. All
detours are posted. Completion date: June 2008.
Interstate 77, Summit County
The White Pond entrance ramp to northbound I-77 in
the city of Akron is closed until mid-July, as part
of a project to widen and reconstruct I-77 from SR
162 (Copley Rd.) to SR 21. The ramp from I-77
northbound to SR 21 southbound is closed until late
September. While the permanent work zone
restrictions remain in place, work is suspended over
the weekend and there will be no additional lane
closures. Detours are posted. Completion date:
September 2008.
Interstate 80, Mahoning County
Widening the roadway and construction of a new
bridge over the Meander Reservoir on I-80, between
SR 45 and the SR 11 interchange. The roadway is
reduced to two lanes in each direction. North Lipkey
and North Turner roads under I-80 are closed. While
the permanent work zone restrictions remain in
place, work is suspended over the weekend and there
will be no additional lane closures. Detours are
posted. Completion date: fall 2009.
State Route 84, Lake County
SR 84, in Willoughby Hills and Wickliffe, is reduced
to one lane in each direction for widening. Traffic
traveling on I-90 westbound is no longer able to
exit onto Bishop Rd., and traffic traveling on
Bishop Rd. is no longer able to enter onto I-90
eastbound. While the permanent work zone remains in
place, crews will not be active between Saturday,
May 26 and Monday, May 28 and there will be no
additional lane closures on these days. Detours are
posted. Completion date: July 2008.
State Route 86, Lake County
SR 86 is closed eastbound between Fay Rd. and SR 84
due to a slope failure. Crews have opened one lane
of SR 86 in the westbound direction only. Though not
an active project, it remains closed pending the
start of construction this summer. Detour is posted.
Completion date: September 2007.
State Route 89, Ashland County
Resurfacing on SR 89, between U.S. 42 and U.S. 30.
SR 89 is restricted to one lane of two-way traffic
using flaggers during work hours until 7 p.m.
Thursday, May 24. Work is suspended over the weekend
and there will be no additional lane closures until
6 a.m. Tuesday, May 29. Completion date: Aug. 15,
2008.
Interstate 90, Lake County
Widening and rehabilitation of I-90 between SR 306
and SR 615. Traffic in both directions is shifted
onto the westbound side of the roadway. The ramp
from SR 615 to I-90 eastbound is closed for the
construction season, as well as the rest area in the
eastbound direction. While the permanent work zone
remains in place, crews will not be active between
Saturday, May 26 and Monday, May 28 and there will
be no additional lane closures on these days.
Completion date: June 2008.
State Route 91, Lake County
Resurfacing on SR 91, between the southern Eastlake
corporation limit and SR 283. One lane of traffic is
maintained in each direction. While the permanent
work zone remains in place, crews will not be active
between Saturday, May 26 and Monday, May 28 and
there will be no additional lane closures on these
days. Completion date: September 2007.
State Route 94/State Route 585, Wayne County
SR 94, at its overlap with SR 585, is restricted to
one lane of two-way traffic using temporary signals
for bridge repair work. Completion date: June 13,
2007.
State Route 181, Crawford County
SR 181, between CR 330 and Middletown Rd., is
restricted to one-lane of two-way traffic using
flaggers for pavement repairs as part of a
resurfacing project. Completion date: July 31, 2007.
U.S. Route 224, Medina County
The lanes of U.S. 224 eastbound are narrowed at its
intersection with Lake Rd. (CR 19) as part of an
intersection improvement project. Two lanes of
eastbound traffic will be maintained at all times.
While the permanent work zone restrictions remain in
place, work is suspended over the weekend and there
will be no additional lane closures. Completion
date: Aug. 31, 2007.
State Route 241, Wayne County
SR 241, just south of Western Rd. (CR 217), is
restricted to one lane of two-way traffic using
temporary signals for bridge repair work. Completion
date: June 13, 2007.
U.S. Route 250, Huron County
Resurfacing on U.S. 250, between U.S. 20 and SR 13.
U.S. 250 is restricted to one lane of two-way
traffic using flaggers until 7 p.m. Thursday, May
24. Work is suspended over the weekend and there
will be no additional lane closures until 6 a.m.
Tuesday, May 29. Completion date: July 31, 2007.
U.S. Route 250, Wayne County
U.S. 250, west of its interchange with U.S. 30, is
restricted to one lane of two-way traffic with
flaggers as part of a resurfacing project.
Completion date: Aug. 31, 2007.
Interstate 271, Summit County
I-271 over SR 8 is reduced to one through lane and
one exit only lane in each direction as part of the
SR 8/I-271 reconstruction project. While the
permanent work zone restrictions remain in place,
work is suspended over the weekend and there will be
no additional lane closures. Completion date: summer
2010.
State Route 309, Crawford and Richland counties
Resurfacing on SR 309, between SR 61 and SR 181. SR
309 is restricted to one-lane of two-way traffic
using flaggers until 7 p.m. Thursday, May 24. Work
is suspended over the weekend and there will be no
additional lane closures until 6 a.m. Tuesday, May
29. Completion date: July 31, 2007.
U.S. Route 322, Cuyahoga County
Widening and reconstruction of U.S. 322 (Mayfield
Rd.) between Lander Rd. and the eastern Mayfield
Heights corporation limit. Traffic is shifted into
one lane in each direction on U.S. 322 between I-271
and Lander Rd. Left turns are permitted only at
signaled intersections. While the permanent work
zone remains in place, crews will not be active
between Saturday, May 26 and Monday, May 28 and
there will be no additional lane closures on these
days. Completion date: fall 2009.
Interstate 480, Cuyahoga County
Resurfacing of I-480, between W. 130th St. and the
Rocky River Bridge. The I-480 eastbound exit ramp at
W. 139th St. and the I-480 westbound exit ramp at W.
150th St. are under construction and have narrowed
traffic lanes. While the permanent work zone remains
in place, crews will not be active between Saturday,
May 26 and Monday, May 28 and there will be no
additional lane closures on these days. Completion
date: May 2008.
Interstate 480, Cuyahoga County
Rehabilitation of I-480 from Tuxedo Ave. to the
Valley View Bridge. The ramp from I-77 south to
I-480 west is closed for the construction season.
The ramp from I-77 north to I-480 west is reduced to
one lane. Traffic on the westbound roadway is
maintained in reduced width lanes. Eastbound traffic
is not currently affected. While the permanent work
zone remains in place, crews will not be active
between Saturday, May 26 and Monday, May 28 and
there will be no additional lane closures on these
days. Completion date: November 2008.
State Route 585, Wayne County
SR 585, just south of Moine Rd. (TR 62), is
restricted to one lane of two-way traffic for bridge
repair work. Two-way traffic will be maintained by
use of temporary signals. Completion date: June 13,
2007.
State Route 611, Lorain County
SR 611, between E. 21st St. and Colorado Ave. in the
city of Lorain, is restricted to one lane in each
direction for a bridge repair project. One lane of
traffic in each direction will be maintained at all
times. While the permanent work zone restrictions
remain in place, work is suspended over the weekend
and there will be no additional lane closures.
Completion date: Sept. 9, 2007.
Interstate 680, Mahoning County
The Wellington Ave. Bridge over I-680 in the city of
Youngstown is closed for reconstruction. Detour is
posted. While the permanent work zone restrictions
remain in place, work is suspended over the weekend
and there will be no additional lane closures.
Completion date: July 31, 2007.
|