Columbus Crossroads Phase I: I-71/670 Project. Hotline 877-381-7071 odot71670.org
7/28/2014
BUSY WEEK ON  COLUMBUS CROSSROADS PROJECT

 

Monday, July 28 - Thursday, July 31 - The Ramp from Cleveland Ave. to I-71 south will be closed – 8 p. m. – 5 a. m. each night.

-Traffic can access I-71 south from 5th Ave. 

-This closure is for bridge painting.

 

Monday, July 28 - Sunday, August 3 – The ramp from I-670 east to Jack Gibbs Blvd. will be closed – 8 p.m. to 5 a.m.

-This closure is for bridge painting.

 

Monday, July 28 - Friday, August 1 – Lane Closures will be in place on the I-71 south and I-670 west ramps to Spring St/Jack Gibbs Blvd. – 10 a.m. to 5.a.m. (no restrictions from 5am to 10am each day)

            -Access to Spring St. and Jack Gibbs Blvd will be maintained during these closures

                -These Closures are for bridge painting.

 

Tuesday, July 29 - Sunday, August 3 – The Ramp from I-670 east to I-71 north will be closed – 8 p.m.- 5 a.m.

-Traffic will be detoured on I-670 east to Leonard Ave. and I-670 west to I-71 north. 

-This closure is for bridge painting.

 

Tuesday, July 29 - Sunday, August 3 – Jack Gibbs Blvd. will be closed – 8 p. m. to 5 a. m.

-Starting at 8 p.m. each night, Jack Gibbs will be closed between Leonard Ave. and the I-670 east exit ramp.

-This closure is for bridge painting.

 

Thursday, July 31 – The ramp from Spring St. Friday, Aug. 1 - Sunday Aug. 3 - The Ramp from Cleveland Ave. to I- 71 south will be closed – 8 p.m. Friday – 5 a.m. Monday. 

-Traffic can access I-71 south from 5th Ave. 

-This closure is for bridge painting.

 

 

Thursday, July 31 – The ramp from Spring St. to I-71 north will close for 4 weeks. 

          -This closure will be in place at 8 a.m. Traffic will be detoured on I-670 east to Leonard Ave. and I-670 west to I-71 north.

            - This closure is for bridge painting.

 

Thursday, July 31 - Sunday, August 3 – Nightly Lane closures will be in place on I-71 north from Spring St. to Jack Gibbs Blvd.

                -At 9 p.m. the right lane will be closed and at 11 p.m. the center lane will be closed.

                -These lane closures are for bridge painting.

 

Thursday, July 31 – I-71 north Closure – 10 p.m. to 5 a.m.

-At 8 p.m. the ramp from Broad St. to I-71 north will close.

-At 10 p.m., the left lane will be closed on I-70 east at Grant Ave.

-Also at 10 p.m., I-71 north will be closed and traffic will be detoured onto

I-670 east to Leonard Ave. and I-670 west back to I-71 north.

           -Police will direct traffic at Leonard Ave.

-All lanes will be reopened by 5am.

This closure is for bridge painting.

 

 

Up-to-date traffic and construction information, 24-hours a day, along with information about I-70/I-71 Corridor can be found at www.odot71670.org

 

Find us on Facebook: http://www.facebook.com/ODOT71670

 

Follow us on Twitter: http://www.twitter.com/ODOT71670​