Work This Week on Crossroads Project
 
TUESDAY April 23 – FRIDAY April 26 (NEW)
At 8 p.m., the ramp from I-670 west to I-71 south will close. Traffic will be detoured to SR 315 south to I-71 south.
By 5 a.m. each morning, the ramp will be back open.
The closure is necessary for work on the bridge piers.
 
TUESDAY, APRIL 23 – WEDNESDAY, APRIL 24 (NEW)
At 8 p.m., the ramp from I-670 east to I-71 north will close. Traffic will be detoured to I-670 east to Leonard Ave. to I-670 west to I-71 north.
By 5 a.m., each morning, the ramp will be back open.
The closure is necessary so crews can work on the bridge deck.
 
TUESDAY, APRIL 23 – THURSDAY, APRIL 25 (NEW)
At 8 p.m., the ramp from I-670 east to I-71 south will close. Traffic will be detoured to I-670 east to Leonard Ave. to I-670 west to SR 315 south to I-71 south.
By 5 a.m., each morning, the ramp will be open.
The closure is necessary for the delivery of steel bridge beams.
 
WEDNESDAY, APRIL 24 – THURSDAY, APRIL 25 (NEW)
At 8 p.m., the ramp from Jack Gibbs Blvd to I-670 west will close. Jack Gibbs Blvd. will also be closed at Cleveland Ave.
By 5 a.m., each morning, the ramp and Jack Gibbs Blvd. at Cleveland Ave. will be open.
The closure is necessary for work on the bridge deck.
 
 
 