Columbus Crossroads Phase I: I-71/670 Project. Hotline 877-381-7071 odot71670.org
7/31/2014
Thursday, July 31 – 71NB Closure – 10pm to 5am

-At 8 p.m., the ramp from Broad St. to I-71 north will close.

-Starting at 10 p.m., the left lane will be closed on I-70 east at Grant Ave.

-Also at 10 p.m., I-71 north will be closed. Traffic will be detoured onto I-670 east to Leonard Ave. and I-670 west back to I-71 north.

                        -Police will be in place to direct traffic at Leonard Ave.

-All lanes will be reopened by 5 a.m.

- This closure is for bridge painting.

 

Thursday, July 31 - Friday, August 1 – Lane Closures will be in place on the I-71 south and I-670 west ramps to Spring St/Jack Gibbs Blvd. – 10 a.m. to 5.a.m. (no restrictions from 5am to 10am each day)

                     -Access to Spring St. and Jack Gibbs Blvd will be maintained during these closures

                        -These closures are for bridge painting.

 

Thursday, July 31 - Sunday, August 3 – The Ramp from I-670 east to I-71 north will be closed – 8 p.m.- 5 a.m.

-Traffic will be detoured on I-670 east to Leonard Ave. and I-670 west to I-71 north. 

-This closure is for bridge painting.

 

Thursday, July 31 - Sunday, August 3 – Jack Gibbs Blvd. will be closed – 8 p. m. to 5 a. m.

-Starting at 8 p.m. each night, Jack Gibbs will be closed between Leonard Ave. and the I-670 east exit ramp.

-This closure is for bridge painting.

 

-This closure is for bridge painting.

 

 

 

 

Thursday, July 31 – The ramp from Spring St. to 71N will close for 4 weeks. 

                     -This closure will be in place at 8 a.m. and traffic will be detoured on I-670 east to Leonard Ave. and I-670 west to I-71 north.

                        -This closure is for bridge painting.

 

Thursday, July 31 – The ramp from Spring St. Friday, Aug. 1 - Sunday Aug. 3 - The Ramp from Cleveland Ave. to I- 71 south will be closed – 8 p.m. Friday – 5 a.m. Monday. 

 

-Traffic can access I-71 south from 5th Ave. 

-This closure is for bridge painting.

 

 

Thursday, July 31 – The ramp from Spring St. to I-71 north will close for 4 weeks. 

-This closure will be in place at 8 a.m. Traffic will be detoured on I-670 east to Leonard Ave. and I-670 west to I-71 north.

                        - This closure is for bridge painting.

 

 

Thursday, July 31 - Sunday, August 3 – Nightly Lane closures will be in place on I-71 north from Spring St. to Jack Gibbs Blvd.

                        -At 9 p.m. I-71 north will be reduced to two lanes. At 11 p.m., I-71 north will be reduced to one lane between Spring St. and Jack Gibbs Blvd.

                        -These lane closures are for bridge painting.

 

Friday, August 1 - Sunday, August 3 – Nightly Lane closures will be in place on 71N from Spring St. to Jack Gibbs Blvd & the Broad St. on ramp will be closed.

-At 9 p.m. I-71 north will be reduced to two lanes. The Broad St. ramp to I-71 north will be closed. The detour will be Hamilton Ave. to Spring St. to I-71 north.

- At 11 p.m., I-71 north will be reduced to one lane.

- The closures are for bridge painting.

 

 

 

Up-to-date traffic and construction information, 24-hours a day, along with information about I-70/I-71 Corridor can be found at www.odot71670.org

 

Find us on Facebook: http://www.facebook.com/ODOT71670

 

Follow us on Twitter: http://www.twitter.com/ODOT71670​