 Temporary Closures

 
The dates, times and closure information below are subject to change based on weather and nightly progress. Please check back often for updates.
 
CCG6A - I-77 over I-490

Overnight Thursday, July 19, crews will close the I-77 south ramp to I-490 east/E. 55th Street from 7 p.m. to 6 a.m. for overhead bridge work. Motorists will be detoured via Woodland Ave. to E. 55th St.

Overnight Wednesday, July 25 and Thursday, July 26 crews will close the I-77 south ramp to I-490 east/E. 55th Street from 7 p.m. to 6 a.m. for overhead bridge work. Motorists will be detoured via Woodland Ave. to E. 55th St.  Through fall 2019, all lanes of I-77 north and southbound over I-490 will be shifted to accommodate bridge demolition and construction operations.

The dates, times and closure information above are subject to change based on weather and nightly progress. Please watch for email updates! 
 
CCG6B - Broadway Ave. over I-77
Friday, July 20 at 8 p.m. through Monday, July 23 at 6 a.m. the following closures will take place on I-77 to install bridge concrete beams at Broadway Avenue:
  • I-77 northbound at I-480. Motorists will be detoured via I-480 west to SR 176 north to I-490 east to I-77 north.
  • I-77 southbound at I-490. Motorists will be detoured via I-490 west to SR 176 south to I-480 east to I-77 south.
  • I-480 east and westbound ramp to I-77 north. Motorists will be detoured via SR 176 north to I-490 east to I-77 north.
  • I-490 east and westbound ramps to I-77 south. Motorists will be detoured via I-77 north to East 30th Street to I-77 south to I-490 west to SR 176 south.
  • I-77 southbound at the SR 21 exit ramp.  Motorists will be detoured via SR 21 south to SR 17 west to I-480 east and back onto I-77 south.
 
Several entrance and exit ramps on I-77 between I-480 and I-490 will remain open through the weekend, however various utility, construction and maintenance related work will cause ramp and lane closures on Saturday and Sunday along this stretch, so local access will be limited.
 
Reconstruction of the Broadway Avenue bridge over I-77 in the city Cleveland will close on Monday, March 5, 2018 (the original date was March 2) with a nine (9) month closure of the structure. During the closure, motorists will be detoured via the new Frontage Road on the west side of I-77. The Frontage Road will be open for two-way traffic during the closure. More info here.
 

 Long Term & Permanent Closures and Restrictions

 
I-90 East Exit to East 22nd Street
The I-90 eastbound exit ramp to East 22nd will remain acessible ONLY by using I-77 north to I-90 east.
E 14th Street Entrance Ramp to I-90 West
This ramp will remain closed thru completion of Innerbelt Construction Contract Group 3. For more info on future plans and timelines, click here.  Detour via the E 9th or Ontario Street ramps to I-90 west.
 
 E 9th Street Entrance Ramp to I-77 South
This ramp will remain closed permanently. For more information on this change, click here.
 
Ontario Street Entrance Ramp to I-77 South
This ramp will remain closed permanently. For more information on this change, click here.