Just in time for the weekend, ODOT will open two more ramps at the I-270/SR 315/US 23 interchanges, one of them brand new: 
  • SR 315 south to I-270 east - New "Shepherd's Hook" Ramp
  • I-270 east to SR 315 north - Loop ramp reopens
The graphic below illustrates how the new ramps will operate. Please note the project is not complete. There are more ramps and bridges to open this year. Final completion is still October/November. Click HERE to view a larger version. 
 
Here's how traffic will be impacted tonight.
THURSDAY, AUGUST 24
  • 7 PM: Ramp from SR 315 North to I-270 East/US 23 will be reduced to one lane.
  • 7 PM: I-270 east will be reduced to three lanes between Sawmill Road and US 23
  • 9 PM: I-270 east will be reduced to two lanes between Sawmill Road and US 23
  • 9 PM: Ramp from I-270 East to SR 315 South will close. The detour is I-270 EB to US 23 to I-270 WB to SR 315.
  • 5 AM: All lanes and ramps open, including the new ramp from SR 315 south to I-270 east and the ramp from I-270 east to SR 315 north.
I-270 eastbound drivers heading to SR 315 north will have to exit much sooner than they're used to. I-270 east to SR 315 north or south must get in the right lane before Linworth Road.