Because of the simplicity
this item of work, no detailed explanation of the item is required in this
manual.
1. Materials.
2. Document location of where material was placed and
lift thickness.
3. Roller weights.
4. Lift thickness.
5. Roller passes.
6. Use a rubber tire roller for the final compaction.
7. Perform the compaction tests according to S-1015.
8. Weigh tickets should be totaled with an initialed and
dated tape attached. Convert to cubic
yards as per 411.04
of the C&MS.
9. Pay and measure according to 411.04
and 411.05.
10. Document on CA-D-1
and CA-EW-12. Do not
duplicate the information on these forms unless necessary.