Uses
and Application
Materials
(804.02)
Construction
(804.03)
Contractor Designed Cement Soil (804.06)
Uses
and Application
- The
construction is similar to lime.
- Use
for soils with a PI<20.
- Mainly
Sandy and Silty Soils.
- A-3-a,
A-4-a, A-4-b, A-6-a, and some A-6-b’s.
- Use
for Stabilizing Long Sections.
- Continuous
sections greater than 20,000 square yards.
- Used
to modify the subgrade to bridge soft areas.
- See
the Subgrade Treatment Chart in Figure 204.H
and the other pertinent sections.
- Use
for average N values as low as 5.
- Average
U of 0.5 tons/ ft2 .
- To
remove ruts > 6 inches (150mm).
A brief outline of the specification requirements follows:
Materials (804.02)
- Use
Type 1 Cement. 701.04
- Use
between 4 to 10 % by weight.
- Plan
will include 6 %.
- Soil
must weigh at least 100 lb/ft3.
- Use
Prime coat for curing at 0.3 gallons per square yard.
- Do
not use the type specified in the supplement; It can leach out during a
rain.
- Use 702.04
Emulsified Asphalt Types RS-1 or RS-2.
Construction
(804.03)
- Limitations
- Temperatures
greater than 40o.
- Material
not frozen.
- No
severe wet conditions.
- If
stabilization specified in spot locations.
- Test
roll with proof roller to locate soft areas.
- Investigate
if rutting is greater than 6”.
- Proof
Roll after stabilization if stabilization is specified throughout the
project.
- See
Subgrade Stabilization Sections in this manual.
Usually use 6 percent cement per 110 pound soil. Use Equation 804.1 to calculate the number
of pounds of cement to use per square yard:
where:
9 ft2
in a square yard
9 ft2 /yd2 x (one inch deep)/12
inches/ft = ¾ ft3/yd2 per one inch deep
D = depth (inches)
WD = average density (lb/ft3)
% = percent cement (expressed as a decimal)
For example, if using 6 % cement, 110 lb/ft3
material, at 16 inch lifts:
¾ x 16 inches x 110 lb/ft3 material x 0.06 = 79
lb/yd2 of cement
Use a square yard canvas to weight the cement once the
pounds per square yards have been determined.
Once you determine that the amount is correct, it may be sufficient to
simply measure the thickness of the cement.
The Contractor must submit a spreading plan to obtain the
correct amount of cement per square yard.
- Apply
the cement and mix into the soil.
- Use
a power driven mixer.
- During
initial mixing.
- 100
% < an inch and 80 % < #4 sieve.
- Depths
9 to 16 inches.
- Do
not add water.
- Second
pass.
- Add
water.
i.
At least + 2 % of optimum.
ii.
Add water within 2 hours of first mixing.
iii.
Insures hydration of the cement.
- May
use one Pass.
- If
the procedure gets the desired results.
- Check
soil for uniform color.
- Complete
the compaction within 3 hours of adding water.
- Do
not use vibration during final rolling.
- Compact
to 98% of the maximum density.
- Use
the one point proctor method in Supplement
1015.
- Measure
the density and take the proctor soil from under the gauge.
- Use
the Ohio Typical Density Curves to pick the maximum density.
- In
some rare cases, a test section may be constructed or the curves developed
in section 804.06
may be used.
- Check
the depth of the stabilization by digging a hole.
- Add
Phenolphthalein to the sidewalls.
i.
Should turn purple.
- Can
use diluted Hydrochloric acid.
i.
Should fizz.
- Cure
the cement for 5 days.
- Make
sure the surface is wet prior to adding prime.
- Will
prevent drying of surface.
- Fine
grading.
- New
spec will require fine grading after curing.
- Construct
the grade an inch high and:
i.
Take off an inch during fine grading.
ii.
Top inch material dries out.
Contractor Designed
Cement Soil (804.06)
Use this section to verify that the soil will increase in
strength when the cement is added to the soil.
Determine strength gain to detail unconfined strengths. This information can be used to make field
adjustments if problems develop in the field.
Normal increases in strength range from 50 psi to 300 psi for Ohio
soils.
The durability testing is for pavement design information.