Specification
Changes
Uses and Application for Lime Stabilized Subgrade
Materials
(206.02)
Limitations, Test Rolling and Spreading (206.03)
Mixing
(206.04)
Compaction
(206.05)
Contractor Designed Lime Soil (206.06 & 205.07)
Specification
Changes
- Added
PN-206 Test Rolling.
- The
construction procedures were slightly modified.
- The
stability issue was referred to the Earthwork Construction Manual.
- Drainage
and maintenance work done according to 203.04.A.
- The
language in 206 was
shortened by referring to 205.
- Prime
coat is used for curing not water.
- Only
specify water when the slurry method is specified.
- Used
for A-7-6 and A-6-b soils with a PI> 20.
Uses and Application for Lime Stabilized
Subgrade
- Lime
is most effective in treating soils with a PI>20.
- A-7-6
and A-6-b’s soils.
- Use
for continuous sections greater than 20,000 square yards.
- Lime
Stabilized Subgrade is used to modify the subgrade to bridge soft areas.
- See Figure 204.H
Subgrade Treatment Chart and the other pertinent sections.
- Use
average N values as low as 10, average U of 1.0 tons/ ft2 and
to remove ruts < 6 inches (150mm).
A brief outline of the specification requirements follows:
Materials (206.02)
- Use
hydrated or quick lime according to 712.04.B.
- 100%
of the quick lime must pass the # 4 sieve.
- Use
between 4 to 8 % by weight.
- Plan
will include 5 % Hydrated.
i.
If quick lime is used
1.
Use 4 %
2.
Use the conversion in 205.08
for payment
- Soil
must weight at least 100 lb/ft3.
- Use
Prime coat for curing at 0.3 gallons per square yard.
- Do
not use the type specified in the spec book.
- It
can leach out during a rain.
- Use
702.04
Emulsified Asphalt Type RS-1 or RS-2.
Limitations, Test Rolling and Spreading
(206.03)
- Limitations
are the same as in 205.03.
- Temperatures
greater than > 40o.
- Material
not Frozen.
- No
Severe Wet Conditions.
- If
stabilization specified in spot locations.
- Test
roll to locate soft areas with grader.
- Investigate
if rutting is greater than 4”.
- If
stabilization is specified throughout the project
- Proof
Roll after stabilization.
- See
Subgrade Stabilization Sections in this manual.
Usually use 5 percent lime per 110 pound soil. To calculate the number of pounds of lime to
use per square yard, use Equation 205.2:
where:
9 ft2
in a square yard
9 ft2 /yd2 x (one inch deep)/12
inches/ft = ¾ ft3/yd2 per one inch deep
D = depth (inches)
WD = average density (lb/ft3)
% = percent lime (expressed as a decimal)
For example, if using 5 % lime, 110 lb/ft3
material, at 12 inch lifts:
¾ X 12 inches X 110 lb/ft3 material X 0.05
= 49 lb/yd2 of lime
Use a square yard canvas to weight the lime once the pounds
per square yards have been determined.
Once you determine the amount is correct, then you may want to just
measure the thickness of the lime. The
Contractor must submit a spreading plan to obtain the correct amount of lime
per square yard.
See the re-agitation requirement for the slurry method. Use the slurry within 24 hours of mixing to
maximize the effectiveness.
Mixing (206.04)
- For
Slurry Method.
- Open
the soil up prior to applying the lime.
- Apply
the lime and mix into the soil.
- Use
a power driven mixer.
- During
initial mixing.
i.
All clods less than 2 inches (50mm).
ii.
Depth 9 to 16 inches.
- Add
water.
- Optimum
for hydrated.
- + 3
% for quick.
i.
Prevents expansion.
- Lightly
compact.
- Cure
with Water for 24 Hours to 7 days.
- Mellows
the soil.
- Re-Mix
the Soil.
- Soil
100 % < 1” and 60 % P- #4 Sieve.
- Add
water to the same moisture contents.
- Check
soil for uniform color.
Compaction (206.05)
- Compact
to 98% of the maximum density.
- Use the
one point proctor method in Supplement
1015.
- Measure
the density and take the proctor soil from under the gauge.
- Use
the Ohio Typical Density Curves to pick the maximum density.
- In
some rare cases, a test section may be constructed or the curves developed
in section 205.07
and 206.06
may be used.
- Check
the depth of the stabilization by:
- Digging
a hole.
- Add
Phenolphthalein to the sidewalls.
i.
Should turn purple.
- Can
use diluted Hydrochloric acid.
i.
Should fizz.
- Cure
the Lime for 5 days.
- Make
sure the surface is wet prior to adding prime.
- Will
prevent drying of surface.
- Fine
grading.
- New
spec will require fine grading after curing
- Construct
the grade an inch high and
- Take
off an inch during fine grading.
- Top
inch material can dry out during cure.
Contractor Designed Lime Soil (206.06 &
205.07)
Use this section to verify that the soil will increase in
strength when the lime is added to the soil.
Unconfined strengths are determined to detail the strength
gain. This information can be used to
make field adjustments if problems develop in the field. Normal increases in strength range from 20
psi to 100 psi for Ohio soils. Consider
adding the durability test for cement to this work to ensure durability.