ITEM 448  ASPHALT CONCRETE

448.01   Description
448.02   JMF Field Adjustments
448.03   Reports
448.04   Acceptance
448.05   Basis of Payment

448.01  Description.  This work consists of constructing a surface course or an intermediate course of aggregate and asphalt binder mixed in a central plant and spread and compacted on a prepared surface.

The requirements of Item 441 apply, except as modified by this specification.

The Department will determine acceptance of the mixture by Lot, based on the composition of random samples taken and tested by the Contractor and verified by the Department.

448.02  JMF Field Adjustments.  Determine the need for any JMF gradation adjustments, provided for in 441.05, from the results of quality control and Department verification tests of the first two acceptance lots.  Following adjustment, the Department will apply the adjusted JMF, for acceptance purposes, to the entire production including the first two lots.  Give the DET written notice of JMF adjustments no later than the end of the first workday following the notification of verification test results of the second acceptance lot.

For projects with less than two acceptance lots or for any JMF that will no longer be used on a project, give the DET written notice of any JMF gradation adjustments within 1 workday following the notification of acceptance test results.

448.03  Reports.  Submit the Quality Control Report according to 441.11 on the workday following the completion of production of each acceptance lot.

448.04  Acceptance.  Refer to Item 403 for acceptance requirements.

448.05  Basis of Payment.  The Department will pay for accepted quantities, completed in place, at the contract prices, or at the contract price as modified in 448.04, as follows:

Item unit Description
448 Cubic Yard (Cubic Meter)  Asphalt Concrete Intermediate Course, Type ___
448 Cubic Yard (Cubic Meter)  Asphalt Concrete Surface Course, Type ___