ITEM 505  PILE DRIVING EQUIPMENT MOBILIZATION

505.01  Description

505.02  Basis of Payment

 

505.01  Description.  This work consists of mobilizing pile driving equipment to and from the project site and, as necessary, to install the required piling.

This work includes the fixed costs that are related to the installation of the required piling.

505.02  Basis of Payment.  The Department will pay for accepted quantities, after the first service pile is installed, at the contract price as follows:

Item           unit                                Description

505          Lump Sum             Pile Driving Equipment Mobilization