ITEM 654 RENOVATING EXISTING SOIL
654.01
Description
654.02
Materials
654.03
Construction Requirements
654.04 Method
of Measurement
654.05 Basis of
Payment
654.01 Description. This work consists of
preparing a suitable seedbed by grading and renovating existing soil, and
furnishing and placing commercial fertilizer, if specified.
Use
removed or excavated materials in the Work when the material conforms to the
specifications; if not, then recycle or dispose of the material according to 105.16 and 105.17.
654.02 Materials. Use commercial fertilizer
conforming to 659.04.
654.03 Construction Requirements. Prepare
the surface area for seed according to 659.10.
If
the Contract Documents require commercial fertilizer, place it according to 659.04.
654.04 Method of Measurement. The
Department will measure Renovating Existing Soil by the number of M square feet
(square meters) completed and accepted.
The
Department will measure Commercial Fertilizer by the number of tons (kilograms)
completed and accepted.
654.05 Basis of Payment. The
Department will pay for accepted quantities at the contract prices as follows:
Item
Unit
Description
654
M Square Feet
Renovating Existing Soil
(Square Meter)
654
Ton
(Kilogram)
Commercial Fertilizer