Importance of Proper Embankment Construction
Importance of Proper Excavation
Embankment Construction Methods (203.05)
Spreading and Compacting (203.06)
Compaction and Moisture Requirements (203.07)
Method of Measurement (203.09)
After many years of solving soil and rock problems throughout the state, the author of this section can assure the reader of ‘One Constant’.
“Soil and Rock Conditions Vary, Vary and
will Vary Again.”
The author could repeat this statement a hundred times throughout this manual and it would be a hundred times too few.
Earthwork consists of roadway excavations (cuts) and roadway embankments (fills) for highways and associated items of work. Earthwork includes all types of materials excavated and placed in embankment, including soil, granular material, rock, shale, and random material. Associated items of work considered to be in the broad range of earthwork that includes: preparation of foundations for embankment, disposal of excavated material, borrow, preparation of the subgrade, proof rolling, rock blasting, base construction, and berm aggregate construction.
If pavement is to remain smooth and stable during years of service under traffic, the earthwork on which it is built must be stable and must furnish uniform support. Where roughness, settlements and other distress develop in pavement during service under traffic, the cause often is a deficiency in the stability of earthwork, which supports the pavement.
uniformity of earthwork is necessary and important to obtain high stability and long-term performance at all locations throughout the length and width of the project. Consider, for example, a highway project where 95 percent of the earthwork was performed in according to the specifications. But 5 percent was non-specification and low-stability material, which appeared in many small areas throughout the project. Pavement roughness and distress developed in these areas during service under traffic loading. Such a project probably would be evaluated by the traveling public as a “rough job” or a “poorly constructed” project. No notice or credit would be given to the 95 percent of the work, which was constructed properly. The entire project might be discredited and be considered poor because of a relatively small proportion of the project was constructed with poor earthwork construction procedures or practices.
The foregoing assumed example is intended to illustrate the need for consistent compliance with earthwork specifications in all areas, both large and small, throughout the length of the project, and throughout the time from the beginning to the end of earthwork construction.
The embankments that ODOT constructs are structures. The success of these structures is directly proportional to the project’s emphasis on correct embankment techniques.
The importance of proper construction practices during construction cannot be overemphasized. Improper construction practices may or may not show up during construction. But, these improper practices will eventually show up at some point during the life of the embankment structure.
The construction requirements in the specifications are written to maximize the embankment structure’s life. When the specifications are ‘not’ followed, the life expectancy will decrease and the future maintenance cost will increase.
This Embankment Structure is shown in Figure 203.A. The Structure consists of three main components:
The Office of Geotechnical Engineering, or a Soils consultant, ensure that foundation integrity and stability is designed into the plans. The pavement is constructed on top of the embankment.
Figure 203.A - Embankment Structure
The embankment that is shown in the plans structurally bridges the foundation and supports the pavement. The stability or structure is built into the embankment by compacting layers of materials in horizontal lifts, as shown in Figure 203.B. These lifts consist of soil, granular material, rock, shale, asphalt, concrete, or recycled materials. The embankment’s resistance to movement relies on the proper construction of these lifts to work together as a unit.
Figure 203.B - Embankment Layers
A condition such as the one in Figure 203.C can occur if an embankment is not properly constructed. When this condition occurs the Factor of Safety is less than 1.0 and the embankment fails.
Figure 203.C - Embankment Failure
A factor of safety is the ratio of the Resisting Forces divided by the Driving Forces, as shown in Equation 203.1.
|
Factors of safety for embankment structures are very low, on the order of 1.2 to 1.5. Figure 203.D illustrates the resisting and driving forces. The weight of the fill works to move the foundation and the embankment clockwise to the right. The internal strength of the embankment layers and the foundation work together to support the pavement. Failure may occur in a circular fashion as shown, in a semi circle, or in a block mode. The basic principles are the same.
Figure 203.D - Factors of Safety
Proper excavation techniques in cut sections are just as important as embankment construction; the only difference is that in the failure mode the rock or soil falls on the roadway instead of the roadway failing.
This is illustrated in Figures 203.E(a) and (b). If a soil cut is cut too steep then the soil can flow on to the roadway as illustrated in 203.E(a). Figure 203.E(a) shows a deep-seated wedge failure. This failure can occur in an embankment condition also.
Figure 203.E(a) – Cut Slope Failure (deep seated wedge)
Figure 203.E(b) – Cut Slope Failure (rotational failed condition)
Figure 203.E(b) details a rotational failed condition on the left. The right side details fixed condition by properly benching and reducing the load. If a rock cut is cut too steep, the rock can fall on the roadway.
Figure 203.F – Falling Debris from Vertical or Nearly Vertical Faces near Roadway
The above rock and soil conditions can be avoided during the design or construction of a project. Ensure that the plan intent is followed in these cut locations on the project. Rock and shale excavations will be detailed under Item 208 Rock Blasting.
The following is a brief summary of the specification changes between the 1997 CMS and the 2002 specifications in Item 203:
One of the biggest changes was the definitions and material requirements of the type of material allowed under the specifications.
In order to properly detail the requirements, it was necessary to divide up natural and recycled material requirements. Too many times in the past Contractors would try to obtain approval for materials that were not intended under the specifications.
A natural material is a material that was created by nature; a material that is mined or excavated and graded is a natural material. A material that is chemically altered by a manufacturing process such as concrete, fly ash, foundry sand, or slag is a recycled material.
Materials are defined in 203.02. As the materials are defined in 203.02, all of the allowed materials are detailed in 203.02.R as “Suitable Materials.” Specific, more detailed material requirements are centralized in 703.16.
In the preceding sections, the material details will be detailed in the specific 203.02 sections for clarity.
If there is any doubt on the condition, status, acceptability, or approval of the materials throughout the following sections, then the project should contact one of the following:
District Engineers of Test at the following Web Site:
http://www.dot.state.oh.us/construction/OCA/DCEList.htm
The Aggregate Section in the Office of the Materials Management at the following Web Site:
http://www.dot.state.oh.us/testlab/Aggregat/Aggregat.htm
The Office of Geotechnical Engineering at the following Web Site:
http://www.dot.state.oh.us/geotechnical/
The definition for natural materials in 203.02.I is as follows: “All natural earth materials, organic or inorganic, resulting from natural processes such as weathering, decay, and chemical action.”
Allowable materials are materials such as clay, silt, sand or gravel. These are allowed as suitable materials and are further defined in 703.16.A.
Department Group Classifications A-4-a, A-4-b, A-6-a, A-6-b, and A-7-6 are allowed. All of these materials are fine graded and have more than 35 percent of the particles passing the number 200 sieve. More detail can be found by examining Figure 203.02.I. These classifications are further defined on the right side of the chart under Silt-Clay Materials
Materials must have a maximum laboratory dry weight of at least 90 pounds per cubic foot (1450 kg/m3). Materials that are less than this weight usually have too much organic matter or clay materials.
Soils that have a liquid limit in excess of 65 or identified as Department Group Classifications A-5, or A-7-5 are not allowed. The A-5 material is highly elastic by virtue of its high liquid limit. The A-7-5 material is highly elastic and subject to volume change.
These materials are defined in 203.03.H as follows: “Natural granular materials includes broken or crushed rock, gravel, sand, durable siltstone, and durable sandstone that can be placed in an 8-inch (200 mm) loose lift.”
These materials are allowed in 203.02.R, Suitable Materials. The material requirements are further detailed in 703.16.B and 703.16.C.
Under 703.16.B, Department Group Classifications A-1-a, A-1-b, A-3, A-3-a, A-2-4, A-2-6, or A-2-7 are allowed. All of these materials generally are mixtures of coarse and fine graded materials. These materials have less than 35 percent of the particles passing the number 200 sieve. More detail can be found by examining Figure 203.02.A. These classifications are further defined on the left side of the chart under Granular Materials.
Granular material classified as A-2-5 is not allowed because of its low weight, high optimum moisture, high LL, low PI, and its propensity to for sloughing.
Allowable materials include durable sandstone and durable siltstone. If these materials meet the ASTM D 4644-87 requirements in 703.16.C, then the material is considered equivalent in strength and durability to other natural materials.
Contact the Office of Geotechnical Engineering to arrange for the appropriate materials testing if sandstone or siltstone is used for this application. The following is a link to their Office:
http://www.dot.state.oh.us/geotechnical/
In 703.16.B, there is an option for the Contractor to use other materials that meet the gradation requirements in section 703.16.B. Section 703.16.C allows Slags and Recycled Portland Cement Concrete to be used as granular material.
Figure 203.02.A - Department Soils Classification Chart
* A-2-5 is not allowed under 703.16.B. A-5 and A-7-5 are not allowed under 703.16.A. See “Natural Soil and Natural Granular Soils” (203.02.H) section in this manual.
** A-4-B is not allowed in the top 3 feet (1.0m) of the embankment under 203.03.A.
With the required test data available, proceed from left to right on the chart Until the correct grouping is found by process of elimination. The first group from the left that fits the test data is the correct classification.
It is sometimes necessary to make field decisions based on very little (if any) laboratory soils information. Or, it may be necessary to verify the accuracy of plan soil borings in the field. In these two cases and on other occasions, it is important to have a basic understanding of how to identify types of soils and granular materials in the field. The following is some, but certainly not all, of the methods that can be used to identify these materials in the field.
Granular soils are easily identified by their particle size in the field. A sample may be taken inside and spread on a table to dry. A rough estimate of the material retained or passing each sieve may be obtained by examining the material when dry: the finer material cannot be separated and can only be distinguished between one another by a settling technique. This can be accomplished by using a hydrometer or by performing a crude settling test. This technique is beyond the scope of this manual.
It is more important, yet harder, to distinguish between a clay and silt material in the field. Clays and silts should be treated and used differently in the field because of their difference in engineering and compaction properties. See the properties of soils in the next section.
A clay material can be easily rolled into a thread at moisture contents at, near, or above the plastic limit of the material. Clays can often be rolled into 1/8 inch (3mm) diameter threads (about half the diameter of a pencil). See the plastic limit test later in this manual for further information. The thread may be easier and may be rolled into smaller sizes as the clay content increases. You may not be able to roll a silt material into a 1/4 inch (6mm) thread no matter what the soil content.
Clay forms hard pieces that cannot be broken by hand pressure when it is dry. Place an irregular piece of dry soil between the index finger and the thumb, and try to break the material. If the material is difficult or impossible to break, it is probably clay. A silt or sandy material will generally break easily with this amount of hand pressure.
Clay fines are generally greasy, soapy, and sticky. Clay dries slowly, while silt will dry faster than clay.
When performing these hand techniques, observe the soil residue found on your hands for further information. If the soil on your hands is difficult to remove and the hands need to be rubbed briskly together to remove the soil, the material is probably a clay. A silt material is generally easily removed from the hands when rubbed together.
A silt material will react to vibration or shaking. Place a small amount of pliable soil in your hand. Hold the material in one hand and drop that hand on the other hand or a hard surface. Water will form on the surface of a silt material. You can also put the soil in a bowl and tap it on a table to get the same result. Clay will not react to this test.
The above crude identification techniques should not replace classification by the laboratory but should be used as a supplement.
If there is any concern, send a sample to the DET for further classification as soon as possible.
The following are general statements regarding the engineering properties of soil and granular materials. Consider these properties when solving field problems.
Granular soils are less affected by the moisture content than clays and silts, have larger voids, and are free draining. Granular materials have relatively larger particles as compared to silts and clays. They are (granular) by weight, and heavy in comparison to the films of moisture that surround them.
Water content has a large effect on the physical properties of fine-grained soils. The Atterberg Limits are used to describe the effect of varying water contents on the consistency of fine-grained soils. See Figure 203.02.B.
Figure 203.02.B - Atterberg Limits
The PI is used to classify soils. Equation 203.2 is an example of how the PI is calculated:
|
Liquid limits as well as plastic limits are the water content at the condition of the test. See the next section.
The following is a brief description of the characteristics of soils in the physical states.
All cohesive soils are compacted at water contents less than the plastic limit of the material. For A-7-6 soils, the optimum moisture content is around the plastic limit minus 3. For A-4 and A-6 soils, the optimum is around the plastic limit minus 5. The optimum moisture content of granular materials ranges between 5 and 10, and for non-plastic silts is around 11.
You can obtain an estimate of the consistency of the material by using the above information and looking at the soil’s water content from the soil borings before the work begins. Keep in mind the water content on the soil borings is the water content at the time the borings were extracted. They should be considered an estimate of the present field conditions.
You can approximate the optimum moisture of a material by the feel of the material in the field.
If the material… |
Then material is… |
Falls apart in small pieces |
Dry of optimum |
Stays together |
At or above optimum |
Breaks into two or three large pieces |
At optimum |
Stays together and there is excess water on hands |
Above optimum |
If the material… |
Then material is… |
Ball cannot be formed |
Below optimum |
Becomes oval |
Above optimum |
Breaks apart into uniform pieces (Some clays will have larger pieces than silts) |
At optimum |
If the saliva… |
Then material is… |
Beads up |
Above optimum |
Slowly sinks in |
At optimum |
Use these methods as estimates; they do not replace compaction testing. These estimates are different for each type of soil (clay, silt, granular).
Each term used in geotechnical engineering has specific meaning and application. Each soil test has specific meaning and application and indicates certain soil properties. Care in using correct terminology will prevent confusion and misunderstanding.
Soils have properties that influence their behavior and value. The properties of soil will vary with its gradation (composition), its moisture content, its vertical position in relation to the surface of the ground, and its geographical location. The more common properties encountered and used in highway work are defined and discussed in Section 203.
Most soils originally were solid rock; time and climate have broken the rock into progressively smaller particles. This can be shown in the laboratory by taking two or three pieces of gravel or stone and pulverizing them. First, sand-size particles can be made, then silt-size particles, and finally clay-size particles. However, chemical changes also take place as nature reduces rock into finer particles. Therefore, clay produced by nature over a period of many years will vary from clay-size material produced in a short time in a laboratory.
By naming and defining sizes of the soil particles, all soil tests are placed on a common ground for comparison. The amount of soil retained or passing each sieve is one of the major tools used in judging, analyzing, and classifying a soil.
The quantities of each are determined by a laboratory analysis that separates the soil into groups of particle sizes. The standard methods of test prescribed by AASHTO T-88 and ASTM D-422 have been used widely in highway engineering and are used by the Department.
The distribution of particle sizes larger than 0.074mm retained on the No. 200 (75 mm) sieve is determined by sieving, while the distribution of particle sizes smaller than 75 mm is determined by a sedimentation process, using a hydrometer to secure the necessary data.
Definitions of sizes used by the Department are the same as established by AASHTO T-88, with the exception of the definition of clay, and are as follows:
Boulders: Larger than 12 inches (300mm)
Cobbles: 3 to 12 inches (75-300mm)
Gravel: Passing 3 inch (75mm) and retained on the No. 10 (2mm) sieve
Sand: Passing the No. 10 (2 mm) sieve and retained on the No. 200 (75mm) sieve
Coarse Sand: Passing the No. 10 (2 mm) and retained on the No. 40 (425mm) sieve.
Fine Sand: Passing the No. 40 (425mm) sieve and retained on the No. 200 (75mm) sieve
Silt: 75mm to 0.005 mm
Clay: Smaller than 0.005 mm
The amount of each soil type (i.e., boulders, cobbles, silt, and clay) contained in a soil mixture determines its texture or feel. Classification of soils by texture must not be confused with classification of soils for engineering purposes. Sometimes they are similar but at other times they may be different. The amount of each soil type in the soil is determined by laboratory tests. These test results are then compared with the texture definitions in use to determine the texture name.
Soil texture is classified after its sieve size is determined. It is possible to make approximations of texture by the feel of moist soil when rubbed and ribboned between the thumb and index finger.
The texture of soil is given to tell as much as possible about a soil in a few words. Using a texture classification, approximations and estimates can be made of many soil properties, such as bearing value, water-holding capacity, probability to frost heave, permeability, etc.
It is the practice of the Department to describe soil components and texture of a soil as follows:
Major components are described as gravel, sandy gravel, gravelly sand, sand, silty sand, clayey sand, sandy silt, silt, clayey silt, silty clay or clay. More than 35 percent of the total sample is required in order to classify a major component. Where two words are used to describe the major component, the second word describes the greater quantity.
Examples: Sand predominates in “silty sand”, ; while silt predominates in “sandy silt”.
Descriptions of secondary components are preceded by the term listed below, according to the percent of total sample indicated:
Term |
Percent of Total Sample |
Trace |
0 – 10 |
Little |
10 – 20 |
Some |
20 – 35 |
And |
35 - 50 |
Examples of material texture descriptions based on component test results are as follows:
Material Components |
Texture Description |
Sand 30%, silt 55%, clay 15% |
“sandy silt with a little clay” |
Sand 8%, silt 55%, clay 37% |
“silt and clay with a trace of sand” |
Gravel 20%, sand 68%, silt 12% |
“gravelly sand with a little silt” |
Gravel 2%, sand 12%, silt 42%, clay 38% |
“silt and clay with a little sand, trace of gravel” |
Internal friction is defined as the resistance to sliding within the soil mass. Gravel and sand impart high internal friction and the internal friction of a soil increases with sand and gravel content. For sand, the internal friction is dependent upon the gradation, density, and shape of the soil particle, and is relatively independent of the moisture content. Clay has a low internal friction, which varies with the moisture content. A power-dry, pulverized clay has a much higher internal friction than the same soil saturated with moisture, since each soil particle can slide on adjoining soil particles much more easily after it is lubricated with water.
Various laboratory tests have been devised to measure internal friction. It is defined as the angle whose tangent is the ratio between the resistance offered to sliding along any plane in the soil and the component of the applied force acting normal (perpendicular) to the plane. Values are given in degrees. Internal friction values range from 0 degrees for clay just below the liquid limit to as high as 34 degrees or more for a dry sand. Very stiff clay may have a value of 12 degrees.
The governing test should be based on the most unfavorable moisture conditions that will prevail when the soil is in service. This “angle of internal friction” is not the same as the natural angle of repose or degree of slope on the soil in fills.
Cohesion is defined as the mutual attraction of particles due to molecular forces and the presence of water. The cohesive force in a soil varies with its moisture content. Cohesion is very high in clay but of little or no significance in silt and sand. Powder-dry, pulverized clay has low cohesion. However, as the moisture content is increased, the cohesion increases until the plastic limit is reached. Then the addition of more moisture reduces the cohesion. By partially over-drying wet clay, most free water is removed and the remaining moisture will hold the clay particles together so firmly and give the soil such high cohesion that a hammer may be required to break the particles apart. These conditions are illustrated, respectively, by the dry dirt road in summer that dusts easily but carries large loads; the muddy, slippery road of spring and fall; and the hard-baked surface of a road immediately after summer rains.
Various laboratory tests have been devised to measure cohesion. Results are usually given in psf (pounds per square foot) kPa (kilopascals) of cross section and may vary from 0 psf in dry sand and wet silt to 2,000 psf (96 kPa) in very stiff clays. Very soft clays may have a value of 200 psf (10 kPa). The governing test should be based on the most unfavorable moisture condition that will prevail during service.
The stability and hence the structural properties of soil are determined largely by the combined effects of internal friction and cohesion. In most soils these combine to make up the shearing resistance. The combined effects are influenced by other basic factors such as capillary properties, elasticity, and compressibility.
All these factors plus the site on which the soil is located determine the moisture content that will prevail in the soil in service. They also govern the load-carrying capacity of a soil, which is the primary concern. The clay-gravel road made up largely of gravel and sand, with a small amount of silt to fill voids and a small amount of clay to give cohesion, illustrates a soil of high bearing value produced by high internal friction due to sand and gravel and high cohesion due to clay. Clay illustrates a soil of low bearing value, because when clay is wet, internal friction is negligible since no coarse grains are present, and cohesion is low since it has been destroyed by moisture. The same clay, air-dry, will have high bearing value due to high cohesion brought about by the removal of moisture.
Capillarity is defined as the action by which a liquid (water) rises in a channel above the horizontal plane of the supply of free water. The number and size of the channels in a soil determine its capillarity. This soil property is measured as the distance moisture will rise above the water table by this action, and will range from 0 in some sand and gravel to as high as 30 feet (9 meters) or more in some clay soils. However, it often requires a long period of time for water to rise the maximum possible distance in clay soils because the channels are very small and frequently interrupted, and the frictional resistance to water is great in the tiny pores.
Moisture in silt soils may be raised by capillarity only 4 feet (1 meter) or so. Since the capillary pores are larger than for clay, a larger quantity of water is raised in a few days rather than over a long period. Silts are considered to have “high capillarity” by Geotechnical Engineers because of this rapid rise of water. The capillary rise in gravels and coarse sands varies from zero to a maximum of a few inches (centimeters).
Complete saturation of the soil seldom occurs at the upper limits of rise of capillary moisture.
Capillarity of a soil and the elevation of the water table under the pavement determine whether the subgrade will become saturated in this manner. Whether or not the subgrade becomes saturated from capillary action (or from condensation, seepage, etc.) determines the bearing value of the soil to a considerable extent. Subgrade saturation by capillarity also determines whether frost heave and similar occurrences in subgrade will create a problem requiring treatment for satisfactory performance in service.
Compressibility and elasticity are the properties of a soil that cause it to compress under load or compaction effort, and to rebound or remain compressed after compaction. Most soils are compressible. Silty soils of the A-5 group are the most elastic of Ohio soils, and make poor subgrades for pavements. Fortunately, A-5 soils are limited in occurrence in Ohio. The A-7 soils in Ohio are moderately elastic, but do not present special problems in embankment or subgrade. A-4 soils are elastic under some moisture conditions, and sometimes present problems of stability during construction, but provide adequate support for pavements where good design and construction practices have been followed.
When a soil elasticity measurement is required, it is determined by special tests that simulate moisture changes and loading conditions anticipated in the field.
When heavy rubber-tire construction equipment moves over an embankment layer foundation of wet fine-grained soil, some movement of the embankment surface occurs. One type of movement, called elastic movement, is described as follows: When the tire moves onto an area, the surface is deformed, and when the tire moves off the area, the surface rebounds, or springs back, with little or no permanent rutting of the surface. Cracking of the surface may or may not occur following this type of movement.
However, cracking usually occurs in cases of “pronounced” elasticity. In the case of pronounced deformation, there is displacement of some surface soil to each side of the tire, with resulting deformation, rupture, cracking, and rutting.
The magnitude of the elastic movement or deformation may depend on one or more of a number of factors, including the following:
Some embankment elasticity and deformation is expected under loaded rubber-tire construction equipment. Moderate movement occurs under heavy equipment on embankments of satisfactory stability, and such moderate movement is not considered detrimental. Greater movement is likely on adequately stable embankments under very heavy equipment usage. Except for specialized situations, such as soft foundation soil at shallow embankment depth under the layer being observed, the greater movement due to these very heavy loads is not detrimental. In general, greater movement under very heavy loads should be permitted without increased restrictions on moisture control.
Moisture control specifications are not intended to limit or restrict the use of very heavy construction equipment on embankment construction. The intent of the specifications is to limit the moisture to obtain a stable embankment.
The amount of elasticity and permissible deformation under any given load varies with job circumstances. For example, for the first layer over a soft original ground embankment foundation, considerable movement under loaded construction equipment is inevitable due to the soft foundation material. The resistance to deformation is more critical in the top portion of embankment, near the subgrade, than in lower portions of the embankment. If the lower embankment layers are low-stability material, such as wet silt, elasticity and deformation of the lower embankment layer must be closely monitored. This would not be necessary if successive embankment layers were of high stability material such as rock, shale, granular material, or dry soil.
Equipment which can be used successfully to test for embankment stability includes: rubber-tired roller, grader, loaded scraper, or loaded truck. Remember, more movement is to be expected under very heavy equipment than under heavy equipment ordinarily used in highway work. When rubber-tire construction equipment such as scrapers, graders or rollers, are being used over the entire general area during normal embankment construction operations, and observation shows no area of questionable stability, it is not necessary to have a piece of testing equipment systematically cover the entire area for the specific purpose of observing stability.
However, when the Engineer or Inspector questions or desires to check further the stability of an area during embankment construction, they are authorized to require the Contractor to move suitable equipment over the area to check for pronounced elasticity or deformation.
The determination of pronounced elasticity or deformation under the action of loaded rubber-tire construction equipment is based on the description given in the first paragraph of this section.
The administration of this requirement should be tempered with sound judgment backed by construction experience. Decisions will be made at project level, and uniform requirement administration must be supervised closely by District Construction Engineers and the Advisory Construction Engineer from the Office of Construction.
Shrinkage refers to the apparent decrease in volume of the soil during its removal from the cut or borrow and its placement in the embankment. The earthwork quantity calculations must be adjusted to account for this apparent loss of material. The following are some of the causes:
Losses due to scalping are usually insignificant and are accounted for in the verification of the original cross sections.
Losses due to settlement of the embankment foundation, where the foundation is compressible, can be calculated by using settlement platforms. A settlement platform is placed on the foundation. The platform is measured throughout the life of the embankment construction. A settlement verses time curve can be used to determine the amount of additional payment that is due. See Figure 203.02.S.
Figure 203.02.S - Settlement Curve
The amount of settlement that occurred over the life of the embankment construction is a function of this Total Settlement Curve. To make the additional embankment payment, multiply the settled amount by the length and width of the settled area.
In this example, the total settlement is as follows:
543.11-542.88=0.23 feet
The amount of shrinkage resulting from increased density in the embankment material may be estimated by using a volume or dry density basis.
The calculation of the shrinkage Factor (SF) is one of the following:
|
|
|
Example of the use of a shrinkage factor:
|
The adjustment due to shrinkage is only used where the material is being paid for as borrow and the material was placed outside of the plan allowed tolerances.
Permeability, a property of soil that allows it to transmit water, is defined as the rate at which water is transmitted by soils. It depends on the size and number of soil pores and the difference in height of water at the point where it enters the soil and the point where it emerges. It is determined by tests on a representative soil sample and expressed as the coefficient of permeability, and it equals the velocity of water-flow in centimeters per second (cm/sec) under a hydraulic gradient of 1. A hydraulic gradient of 1 exists when the pressure head (or height of water) on the specimen in centimeters divided by the depth of the specimen in centimeters equals 1.
The permeability of a soil varies with such factors as void ratio, particle size and distribution, structure, and degree of saturation. Obviously, the permeability of a particular soil will vary with the degree of compaction since this influences the size of the soil pores. A particular soil loosely packed will be more permeable then the same soil tightly packed. Nature produces these differences, in connection with shrinkage forces that may be present, by surface freezing in winter (loosening a soil) and by repeated wetting and drying in the summer (consolidating the soil).
The coefficient of permeability, k, is used to determine the quantity of water that will seep through a given time and distance under a known head of water, by use of Equation 203.6:
|
or
Q, the quantity
of water that will seep, can be found by
Equation 203.7 :
|
where:
Q = quantity of water, in cubic centimeters (cm3)
k = coefficient of permeability, in centimeters per second (cm/sec)
L = thickness of soil, in centimeters, through which flow of water is determined under hydrostatic head H;
A = cross sectional area of material, in square centimeters (cm2);
t = time, in seconds (sec).
Tile can drain very porous soils, such as sands that have a k, in (cm/sec), of 1.0 to 10-3 (0.001). Silty and clayey sand soils have a k of about 10-3 (0.001) to 10-7 (0.0000001). Highly cohesive clays have a k of less than 10-8 (0.00000001). It is difficult, if not impossible, to reduce the water content of soils by tile drains when the permeability coefficient is less than about 10-3 (0.001). For earth dams, the U.S. Bureau of Reclamation classifies soil with k values about 10-4 (0.0001) as pervious and soil with k below 10-6 (0.000001) as impervious.
Soil Group classifications A-6a, A6b and A-7-6 are considered impervious.
The plastic limit (PL) of soils is the moisture content at which a soil changes from a semisolid to a plastic state. This condition is said to prevail when the soil contains just enough moisture that it can be rolled into 1/8 inch (3.18 mm) diameter threads without breaking. The test, ASTM D-424 or AASHTO T-90, is conducted by trial and error, starting with a soil sufficiently moist to roll into threads 1/8 inch (3.18mm) in diameter. The moisture content of the soil is reduced by alternate manipulation and rolling until the thread crumbles.
Clay content governs the plastic limit. Some silt and sand soils cannot be rolled into 1/8 inch (3.18 mm) threads at any moisture content; these have no plastic limit and are termed non-plastic. The test is of no value judging the relative load-carrying capacity of non-plastic soils.
A very important change in load-carrying capacity of soils occurs at the plastic limit. Load-carrying capacity increases very rapidly as the moisture content is decreased below the plastic limit. On the other hand, load carrying decreases very rapidly as the moisture content is increased above the plastic limit.
The liquid limit (LL) is the moisture content at which a soil passes from a plastic to a liquid state. The test, ASTM D-423 or AASHTO T-89, is performed by determining, for a number of moisture contents, the number of blows of the standard cup needed to bring the bottom of the groove into contact for a distance of above 0.5 inch (12.7 mm). These data points are then plotted and the moisture content at which the plotted line (called flow curve) crosses the 25-blow line is the liquid limit.
Sandy soils have low liquid limits of the order of 20. In these soils the test is of little or no significance in judging load-carrying capacity.
Silts and clays have significant liquid limits that may run as high as 80 or 100. Most clays in Ohio have liquid limits between 40 and 60.
High liquid limits indicate soils of high clay content and low load-carrying capacity.
Liquid limit can be used to illustrate the interpretation of moisture content as a percentage of the oven-dry weight of the soil. See an example in the previous section on liquid limit.
The plasticity index (PI) is defined as the numerical difference between liquid limit and plastic limit. Calculation details are included in ASTM D-424 and AASHTO T-90. The plasticity index gives the range in moisture contents at which a soil is in a plastic condition. A small plasticity index, such as 5, shows that a small change in moisture content will change the soil from a semisolid to a liquid condition. Such a soil is very sensitive to moisture unless the combined silt and clay content is less than 20 percent. A large plasticity index, such as 20, shows that considerable water can be added to the soil before it changes from a semisolid to a liquid.
When the liquid or plastic limit cannot be determined or when the plastic limit is equal to or higher than the liquid limit, the plasticity index is considered non-plastic (N.P.).
The moisture conditions at the plastic limit and liquid limit, and the plasticity index, often are called the “Atterberg Limits” (After Atterberg, the originator of the test procedures).
The following is a brief description of the materials in each classification group detailed in Figure 203.02.A.
The typical material of this group is a well-graded mixture of stone fragments of gravel, coarse sand, fine sand, and a non-plastic or feebly plastic soil binder. However, this group may also include the same material without the soil binder.
This material consists of predominantly stone fragments or gravel, either with or without a well-graded soil binder.
This material consists of predominantly coarse sand either with or without a well-graded soil binder.
The typical material of this group is fine beach sand without silty or clay fines or with a very small amount of non-plastic silt. The group also includes stream-deposited mixtures of poorly-graded fine sand and limited amounts of coarse sand and gravel. These soils are sometimes difficult to compact similar to the A-4 group. The fineness of the material and the silt fines make stabilization difficult. See the group A-4 for further explanation.
This material consists of mixtures of coarse and fine sand with limited amounts of silt of low plasticity.
This material consists of a wide variety of “granular” materials which are borderline between Groups A-1 and A-3 and the silt-clay materials of Groups A-4, A-5, A-6 and A-7. It includes all materials containing 35 percent or less passing the No. 200 (75mm) sieve which cannot be classified as A-1, A-3 or A-3a, due to fines content or plasticity (or both) in excess of the limitations for those groups.
This material consists of various granular materials containing 35 percent or less passing the No. 200 (75mm) sieve and with a negative No. 40 (425mm) portion having the characteristics of the A-4 and A-5 groups.
This material consists of materials such as gravel and coarse sand with silt contents of plasticity indexes in excess of the limitations of Group A-1, and fine sand with non-plastic silt content in excess of the limitations of Group A-3. A-2-5 soils are unsuitable embankment material under 703.l6.B because of its low weight, high optimum moisture, high L.L., low P.I., and its propensity to sloughing in service.
This material consists of materials similar to those described under Subgroups A-2-4 and A-2-5 except that the fine portion contains plastic clay having the characteristics of the A-6 or A-7 group. The approximate combined effects of plasticity indexes in excess of 10 and percentages passing the No. 200 (75mm) sieve in excess of 15 are reflected by group index values of 0 to 4.
The typical material of this group is a non-plastic or moderately plastic silty soil usually having 75 percent or more passing No. 200 (75mm) sieve. This group also includes mixtures of fine silty soil and up to 64 percent of sand and gravel retained on No. 200 (75mm) sieve. The group index values range from 1 to 8, with increasing percentages of coarse material being reflected by decreasing group index values. The A-4 group soils are usually very difficult to compact or stabilize. Minimizing the water content to obtain the required density and stability usually works. It is not unusual, nor is it a change in condition, to have difficulty in stabilizing or compacting these soils. This condition should have been expected for this type of material.
Contains less than 50 percent silt sizes, while group A-4b contains more than 50 percent silt sizes. A-4b is only allowed 3.0 feet (1.0m) below subgrade elevation because of frost heave potential.
The typical material of this group is similar to that described under Group A-4, except that it may be highly elastic as indicated by the high liquid limit. The group index values range from 1 to 12, with increasing values indicating the combined effect of increasing liquid limits and decreasing percentages of coarse material. This soil is unsuitable by 703.16.A for use as embankment material because of its elasticity.
The typical material of this group is a plastic clay soil usually having 75 percent or more passing the No. 200 (75mm) sieve. The group includes also mixtures of fine clayey soil and up to 64 percent of sand and gravel retained on the No. 200 (75mm) sieve. Materials of this group usually have high volume changes between wet and dry states. The group index values range from 1 to 16, with increasing values indicating the combined effect of increasing plasticity indexes and decreasing percentages of coarse material.
Contains material with plasticity index of 15 or less, and subgroup A-6b contains material with a minimum plasticity index of 16.
The typical material of this group is similar to that described under Group A-6, except that it has the high liquid limit characteristics of the A-5 group and may be elastic as well as subject to high volume change. The range of group index values is 1 to 20, with increasing values indicating the combined effect of increasing liquid limits and plasticity indexes and decreasing percentages of coarse material.
Includes those materials with moderate plasticity indexes in relation to liquid limit and which may be highly elastic as well as subject to considerable volume change. This soil is unsuitable by 703.16.A because of its elasticity.
Includes those materials with high plasticity indexes in relation to liquid limit and which are subject to extremely high volume change.
Slags are by-products from manufacturing steel or iron. Under 203.02.Q, air-cooled blast furnace slag (ACBF), granulated slag (GS), open hearth (OH) slag, basic oxygen furnace (BOF) slag, and electric arc furnace (EAF) slag that meet the requirements in 703.16 are allowed under Item 203.
Air Cooled Blast furnace slag is a by-product from making iron. It is a very hard and durable aggregate containing visible holes. ACBF slag may have maximum dry weight of about 80 lbs/ft3 (1280 kg/m3), and is lighter than most soils.
ACBF slag can produce a green, yellow, white, or black runoff; the color is usually pH driven. This runoff can also smell like rotten eggs, and usually goes away in about six months (but not always). The runoff may exceed the allowable limits under the Clean Water Act.
The potential for the runoff to exceed the Clean Water Act and Supplement 1027 is based on the following factors:
To minimize this problem in embankment construction, ACBF slag must pass the Sulfur Leachate Test detailed in Supplemental Specification 1027. The manufactures are required to certify that their material meets this requirement. Contact the District Testing Engineer at the following link for verification that the material may be used:
http://www.dot.state.oh.us/construction/OCA/DCEList.htm
The project can also contact the Aggregate Section of the Office of Materials Management at the following link:
http://www.dot.state.oh.us/testlab//
Further details about the potential problems can be found in Other Wastes and Environmental Considerations in Appendix 202 “Regulated Waste Requirements” of this manual.
Granulated Slag (GS) is a slag by-product of making iron similar to air-cooled blast furnace slag. GS is iron slag has been quenched with water during the cooling process instead of air-cooling. It is a very light and brittle material, almost like powder in the pre-compaction condition. After compaction, it is very hard, durable, and almost impermeable. This material sets up like concrete in service. The maximum dry weight is around 50 lbs/ft3 (800 kg/m3).
Steel slags are by-products of making steel. There are three kinds of steel slag defined in 203.02.Q: OH slag, BOF slag, and EAF slag OH Slag is the slag that was produced mainly pre-1970. But some OH slag was made in the 1970’s BOF and EAF slags are newer and faster processes for making steel. However, some BOF plants were in operation in the late 1950’s.
The problems associated with steel slags are worse for EAF and BOF slags than for OH slag. The process for making OH slag is slower than the other two materials. This slower process allows more of the harmful chemicals are to be burnt out of the OH slag. Consequently, OH slag is a better product for non-bound applications for Department work.
Some steel slags can expand, clog up underdrains, or have a high pH runoff. The specifications were written to minimize these problems. The following factors were considered when writing the specification requirements:
Further details can be found in Other Wastes and Environmental Considerations in Appendix 202 “Regulated Waste Requirements” of this manual. OH, BOF, and EAF slags may be used in embankment construction if the materials comply with section 703.16.
Section 703.16 requires that OH, EAF, and BOF slag be completely blended with natural soil or natural granular material. For OH slag, the blend must be at least 30 percent natural soil or natural granular materials. For BOF or EAF slags, the blend must be at least 50 percent natural soil or natural granular material.
The OH, EAF, and BOF slag must also comply with Section 703.15, which states that the aging, stockpiling, deleterious substances, and crushing requirements of 703.14 apply.
OH, EAF, and BOF slag and blends are further restricted in 203.03.E. These materials must be at least 1.0 foot (0.3m) below the underdrains to minimize underdrain clogging.
All of the above restrictions minimize the factors that can lead to expansion, clogged underdrains, or high pH runoff problems.
These materials replace the old granular embankment requirements under the 1997 specification book. The old requirements were too loose and just about any material could pass as granular material, even though it may not fit the engineering or designed need in the plans.
In 703.16.C, the following material kinds are allowed: limestone (CCS), gravel, ACBF Slag, durable sandstone, durable siltstone, GS, or blended natural soil or granular materials with OH, BOF, EAF, or RPCC.
Durability requirements for sandstone and siltstone were previously covered in this manual under “Natural Granular Materials 203.02.H”. The slag requirements were also previously covered in “Slag Materials 203.02.Q” of this manual. RPCC will be covered later in this manual and must be blended similar to the slags. GS was covered earlier and is not required to have a specific gradation.
Six different gradations or types are available for use in construction.
i. Less expensive and widely available.
i. Using in swamp treatment construction.
ii. Used with wick drains.
i. Without great difficulty.
i. Without great difficulty.
i. See Figure 203.02.C Fine Material Migration.
ii. See Figure 203.02.D Preventing Piping.
i. See Figure 203.02.C Fine Material Migration.
ii. See Figure 203.02.D Preventing Piping.
iii. Use 712.09 Type D Geofabric.
i. This material can save money and will work.
Figure 203.02.C - Fine Material Migration
Figure 203.02.D - Preventing Piping
The specifications for rock did not change from the 1997 CMS. The following rock description is in the 2002 specifications: “Sandstone, limestone, dolomite, glacial boulders, brick, and RPCC too large to be placed in an 8-inch (200 mm) loose lift.”
The construction of rock fills are different than the construction of soil or shale fills; therefore, it is important to clearly identify them in the field.
It is important to understand the differences in these materials and to have a basic understanding or their origins. The following is a brief description:
Almost all rock in the state of Ohio is sedimentary rock. Sedimentary rock is formed by cementation, precipitation from solutions, or by consolidation.
Sandstone is a deposition of sand from rivers, wind, or oceans. This material was cemented together under earth pressure or consolidation. Coarse sandstone can be readily identified by the sand grains in the field. Fine-grained sandstone can be confused with siltstone or limestone.
Limestone is calcite formed from ocean deposits of sea organisms (seashells) that were cemented chemically and or by pressure. Chert is a metamorphic form of limestone. Dolomite is limestone with magnesium and calcium carbonate.
Limestone or Dolomite can be readily identified by using a solution of diluted hydrochloric acid. When hydrochloric acid is dropped on the limestone or dolomite the acid will fizz or bubble. The amount of fizzing depends on how much calcium is in the rock. A pure dolomite may not fizz unless the fines of the rock are tested.
Rock boulders are materials brought from Canada during the glaciers and can consist of just about any stone. The amount of earth pressure or chemical crystallization greatly influences the hardness of the stone.
Almost all rock will have a ringing sound with a rock hammer. However, some punky or loosely cemented rock will not ring.
By definition in the 2002 CMS shale is: “Laminated material with a finely stratified structure formed by the natural consolidation of soil. For the purpose of this specification, the following bed types are also considered as shale: mudstone, claystone, siltstone, and clay bedrock.”
This definition for shale has not changed from the 1997 specifications. However, the way we evaluate the material in the field has changed. In the past, shale was identified and compacted “As Directed by the Engineer”. The new approach gives the Engineer a systematic approach to evaluate the shale to ensure long-term durability of the shale fill.
It enables the Engineer to identify these materials and to distinguish between durable, nondurable, soft, and hard shales.
Shale is a sedimentary material that consists of silt or clay particles. Shale was formed when earth pressure squeezed water out of silt and clay mud. In short, shale is consolidated mud. In addition, some shale may be crystallized or cemented together into a stone like form.
The following procedure is detailed in 703.16.D. Shale is evaluated for durability and hardness as follows:
Obtain a typical 6-inch (150 mm) diameter piece of shale.
i. Then try to break the shale broken down by hand pressure.
ii. Refer to the following table to distinguish between hard durable and non-durable shale:
If
material retained on |
Then
shale material… |
75% or less |
is soft shale |
more than 75% |
will be tested for hardness |
i. Roller centrifugal force divided by the roller width.
ii. The Contractor must provide verification of the force.
If
% of shale that breaks down is… |
Then
material is… |
more than 40 |
Hard non-durable or soft shale |
40 or less |
Hard durable shale |
Different materials will always be mixed together in a fill situation. However, this hardness or durability test will give the project a good indication of how the material should break down during compaction. It also provides a ready means to determine the test method to use for compaction acceptance. The following is a summary.
i. Break down and test like granular material.
Further descriptions are detailed in Supplement 1015 “Compaction Testing of Unbound Materials” in this manual.
The following table, based on color alone, can be used for the expected general condition of shale:
Color |
Expected
Shale Condition |
Red |
always soft non-durable |
Green |
1/3 Soft non-durable |
Grey |
1/3 Soft
non-durable |
Black |
1/2 Soft
non-durable |
Of course, this should never be used as acceptance criteria. These numbers will change depending the project location and geologic formation.
This section did not change from the 1997 CMS version.
By definition, random materials are: “Mixtures of suitable materials that can be placed in 8-inch (200 mm) loose lifts.”
Recycled asphalt concrete is allowed if the material is less then 4 inches and is blended with at least 30 % natural soil or natural granular material. The mixing and maximum size requirements are used to minimize the effects of water on the asphalt consistency. Place a piece of asphalt in a bucket of water and see what happens.
In addition, this material is restricted in 203.03.A & B.
Recycled Portland Cement Concrete is allowed if the material is blended with at least 30% natural soil or natural granular material. Additional mixing requirements are in 203.06.D when used as random material. This material is further restricted in 203.03.B &E. This material can clog underdrains and produce a lime rich high pH runoff similar to steel slags as discussed earlier.
This material is required by law. The legal contamination level of this material is listed in 203.03.I.
This material is usually found around underground storage tanks. The level of contamination is so low that you may not be able to see or smell the petroleum in the soil.
Section 203.03.I requires that an environmental consultant review the proposed use and test the material. Submit the report to the Chemical Section in the Office of Materials Management at the following Web Site for approval:
http://www.dot.state.oh.us/testlab/Chemical/Chemical.htm
Coal is a very lightweight material and is not very durable. It is allowed in natural embankment materials when it comprises less than 10% of the blend. It is impossible to keep this material out of the fill on large earthwork construction projects.
The 2002 CMS defines recycled materials as fly ash, bottom ash, foundry sand, recycled glass, tire shreds, or other materials or manufacturing by-products not specifically named as suitable materials in 203.02.R.
The construction and acceptance details are in Supplement 871. These materials have levels of contamination that must be controlled and are regulated by law. Like all other materials ODOT uses, these materials are restricted and have certain engineering properties that must be accounted for in the specifications.
A general discussion of the specification is in section “Recycled materials” of Appendix 202 of this manual. The specification can be found at the following web link:
http://www.dot.state.oh.us/construction/OCA/Specs/SS
and PN 2002/default.htm
The specification requires environmental and geotechnical approval. Submit the environmental report to the Chemical Section in the Office of Materials Management at the following Web Site for approval:
http://www.dot.state.oh.us/testlab/Chemical/Chemical.htm
The Geotechnical Report and materials acceptance is approved by the Office of Geotechnical Engineering. The Office of Geotechnical Engineering is located at the following Web Site:
http://www.dot.state.oh.us/geotechnical/
Figure 203.02.N is a typical application of recycled materials. These materials are used in the inner core of the embankment structure. This controls the chemicals leachate and minimizes the detrimental engineering properties.
Figure 203.02.N - Typical Cross Section for Recycled Materials
Figure 203.02.Fire, details what can go wrong if one uses a recycled material in the wrong fashion. Read the article and be careful. Further discussion about the recycled material is beyond the scope of this manual.
Figure 203.02.Fire - Tire Fire
Figure 203.02.Fire - Tire Fire
Section 203.03 lists materials restricted by the specifications. These restrictions ensure that the embankment structural integrity is sound in the short and long term. Keep in mind that what seems to be a good product in the field may have serious long-term consequences once in place. Many of these restrictions were detailed in the previous sections in this manual.
Many embankment materials are allowed in several locations throughout the embankment structure. These allowable material types are further restricted in the top 2 to 3 feet of the embankment to ensure long-term structural integrity of the pavement.
Some of the general reasons for these restrictions are:
This section details general information about earthwork construction. No explanation is needed for most of this section except for the following subsection.
It is vital to the embankment for the Contractor to maintain a well-drained construction operation. Contractor’s can provide proper drainage without an enormous effort.
Here are some relevant sections from the specifications on page 103.
“Maintain a well drained embankment and excavation operation…… Construct the embankment with sufficient cross-slope to drain in case of rain.”
Maintained cross slopes ensure that the rain runs off the embankment construction area instead of filtering into the embankment. It is difficult to remove water once it is in the embankment . Further embankment construction is compromised once the existing embankment is saturated.
Using a saturated embankment as a haul road can destroy the embankment structure and density. The following verbiage is on page 103.
“If rain saturates the embankment construction, stay off the embankment construction until the embankment dries or stabilizes. Expedite the construction by removing the saturated embankment or dry the embankment by scarifying, plowing, disking, and recompacting the embankment.”
The specifications continue to give the project significant leverage to use with the following passage on page 103 of CMS.
“Throughout the embankment construction operation and at the end of each day’s operation, shape to drain, compact, and re-compact the work area to a uniform cross-section. Eliminate all ruts and low spots that could hold water.
If using embankment construction or cut areas to haul on, continuously move the hauling equipment around on the area to take advantage of the compactive effort. Continually re-grade and compact the haul roads and maintain the construction according to 105.12 and 105.14.”
Contractors will use are a multitude of excuses to avoid maintaining a well-drained embankment area. Some of them are legitimate and some are not. The project will have to use common sense in evaluating them.
The 1997 specifications were not as specific as today’s language. The above specification language was added to significantly improve the project’s leverage concerning this issue.
Plans will often have fill restrictions that mandate the monitoring of the fill height. The plans may call for limiting the fill construction to 3 to 5 feet a week, and may require waiting periods of 30 to 90 days.
In any case, these restrictions usually mean that the embankment will be constructed on a soft foundation. By limiting the load, it allows the foundation to consolidate slowly and allows the pore pressure to dissipate so that the embankment does not fail.
In many cases, it is required that the project monitor the fill height, pore water pressure, and settlement verses time. Figure 203.04.G shows such a plot.
Figure 203.04.G - Settlement Plot
On the horizontal axis is a plot of time, usually plotted in weeks. There are three simultaneous plots on the vertical scale.
Settlement is plotted on the lower half of the drawing. The majority of plans will call for a certain percentage of consolidation or a number of days. The number of days can be waived if a certain percentage of consolidation is achieved.
A best-fit line is drawn between points A and B once the settlement is plotted. This line is then extrapolated to point C, which is the anticipated flattening point of the curve.
As an example, ODOT is asked to estimate the consolidation in week 5. The total settlement that has occurred to the 5th week is 2.5 feet. By extrapolation, the settlement is predicted to stop at 3.0 feet. Therefore the consolidation is 2.5/3.0 = 83 %. If the required consolidation is 95 % then more readings are required.
The designer should always give the consolidation percentage to construction personnel.
Pore water pressure and fill height may be monitored in some cases. In Figure 203.04.G, the fill height is 25 feet and was completed in week 3. If the pore pressure is in excess of the fill height, then stability is probably going to be a problem.
The project engineer should obtain the maximum pore water pressure from design prior to the beginning of the project. Notice in Figure 203.04.G that the pore pressure dissipated from week 4 to week 5.
The specifications have changed regarding the treatment of an embankment foundation. There is a minimum compaction requirement for all foundations that require scalping.
If you recall from section 201.04, scalping is not required if the fill height is greater than 9 feet (3m) and the existing slope is 8:1 or flatter. Both conditions must apply for the areas to be left un-scalped. Figure 203.05.A shows this condition.
Figure 203.05.A - Scalping Not Required
In Figure 203.05.B, the fill height has been changed to 9 feet or less. In this situation, the embankment foundation would require scalping then compaction.
Figure 203.05.B - Foundation Compaction is Required
The compaction requirement is 95 percent of standard proctor or 95 percent of the test section maximum value. This minimum value is easily achieved. An alternate method may need considered if density cannot be achieved.
Foundation conditions are occasionally encountered that require treatment to secure stability either within or beyond the contract documents. Two general cases are:
The nature and degree of the foundation instability may vary considerably.
The first step in determining the proper treatment for a soft foundation and securing embankment stability is to determine and consider the following:
The following types of corrective measures have been successfully used for many years. Measures required to correct unstable foundations often are apparent when the cause and extent of the instability are known. The following sections consider three different situations that occur during construction:
The higher the fill height above the foundation, the better chance the project has in bridging over soft foundation locations with very little additional expense.
Section 203.05 allows the Engineer to increase the lift thickness to bridge soft foundation locations. The specifications refer to areas that do not support the weight of the trucks or hauling equipment (areas with less than 12” (0.3m) of rutting or a moderately soft foundation). For areas with more than 12 feet (4m) of fill, this method should be the first alternative utilized.
Section 203.05 allows the following technique when placing material over the soft foundation:
Manipulate, blade, distribute, level, and doze the material until the area is stabilized.
This is standard practice in soft foundation locations. Density controls during this initial construction are not required. If the soft foundation is just wet and does not have standing water, then soil dryer than optimum may be used.
If the foundation has standing water, consider placing construction underdrains or ditches to drain the soft areas (if the area can be drained). If the areas cannot be drained then use rock, granular material, or hard durable shale in 1 to 3 foot lifts (0.3 to 1 m).
Observe the embankment stability once the bridging material is in place, and make adjustments as required. Reevaluate the conditions at the 6-foot (2m) to grade condition.
Investigate the source of the problem. Evaluating foundation conditions are similar to evaluating the condition of a subgrade. Before determining the solution, first evaluate the foundation conditions by digging test pits, evaluating the soil borings and observing the rut depth.
Use the section “The Investigation” under Item 204 of this manual, Figure 204.G Subgrade Test Pit Investigation and Figure 204.H Subgrade Treatment Chart to help evaluate the foundation.
Determine the average N, average U, and rut depth values using the above sections. Evaluating soft subgrade and soft foundations are similar with a slight twist. If the soft material is less than 2 feet (0.6m) in depth, remove it and replace with soil.
If the average U > 0.5 tons/ft2, average N > 5, and the rut depth is less than 6 inches (150mm), then use an initial thick lift of soil of about 1 to 3 feet (0.3 to 1m). The soil should be less than optimum moisture.
Do not use soil to bridge areas with standing water or in conditions where some embankment has already been placed as in the previous section.
If the soil conditions are lower than these values or the rut depth is more than 6 inches (150mm), then use an initial thick lift of 1 to 3 feet (0.3 to 1m) of rock, granular material, or hard durable shale.
Drain the soft foundation by using construction underdrains or ditches, if the slope allows the area to be drained. Continue to evaluate the conditions when constructing the remaining fill, and adjust when required according to the next section.
If the source of the problem has not been previously evaluated, then investigate the source of the problem as detailed in the previous section.
Determine the average N, average U, and rut depth values. Again, evaluating soft subgrade and soft foundations are similar with slight twists.
To determine the correct fix, use the Subgrade Treatment Chart in Figure 204.H and find the correct undercut depth or stabilization depth.
Subtract the fill height (F) from the total undercut depth (UT) to determine the required undercut (RU) in the foundation. See Figure 203.05.C
Figure 203.05.C - Fill Undercut Depth
Given:
New Construction Project
2 foot (0.6m) of fill left.(F)
U=0.5 tons.ft2, N=5 and Ruts>6 inches (150mm)
From Figure 204.H Subgrade Treatment Chart Undercut depth = 3 feet (1m). (UT)
Solution:
Undercut 1 foot (RU) and place 3 feet (1.0m) of Granular Material (UT). As an alternative, consider placing 2 foot of fill then using 16” of Cement Stabilization.
Severe soft foundations cannot be constructed without using rock or granular material. These conditions usually are in standing water or even underwater. Construction equipment either gets buried in the areas or cannot operate in these locations. Peat deposits or swampy areas that contain organic soil with high moisture are the norm in these locations.
Unless these areas are called out in the plans, it is best to call the Office of Geotechnical Engineering or the District Geotechnical Engineer to evaluate the depth and extent of the required undercut.
This section examines two different methods to remove and replace this soft material.
The following is a brief description of the methods of construction of these two.
Figure 203.05.D - Soft Foundation Total Excavation Method
Figure 203.05.E - Soft Foundation Partial Excavation and Displacement Method
Trenching and backfilling is performed progressively across the soft areas and coordinated to leave an open trench that does not exceed the working length of the excavation equipment. As denoted in the figures, the minimum gap is 15 feet (5 m).
The fill is constructed by a method of end dumping to the elevation designated in the plans or to an elevation of about 1.0 foot (0.3 m) above the water level. If stability is achieved at this elevation, construct the remaining areas according to the embankment requirements.
If the excavation hole immediately collapses, immediately shove the end-dumped material in the hole using a dozer.
Excavate the unsuitable material ahead of the fill. End dump for the full embankment width to advance the operation in a straight line. This avoids the entrapment of unsuitable material beneath the fill.
The material used for this operation may be granular material or rock. Usually Granular Material Type C or D is used for these conditions. Dump Rock is usually specified for depths greater than 10 feet (3.3m). See Figure 203.02.C Fine Material Migration and Figure 203.02.D Preventing Piping.
The unsuitable excavated material may be temporarily left in place or used for flattening adjacent slopes outside the plan lines. This material must be either shaped into the final slope or disposed of 2 weeks prior to paving the project.
Excavation is paid by the cubic yard (cubic meter). Include the cross hatched area in the figures for the excavation payment.
The granular material is usually paid for by the ton. If the plans specify the payment by the cubic yard, then the project may elect to use a conversion factor to convert the payment to tons.
The language for benching in the 2002 CMS is more explicit than in the previous CMS. This new language was put in CMS to ensure that benching is properly performed in the field. Figure 203.05.F details where benching is required. Benching is required for all embankments placed on or against a slope steeper than 8:1. Of course, the existing slope has to be scalped first. This applies on all embankment areas whether the existing embankment cross slope is in the transverse or the longitudinal direction.
Figure 203.05.F - Benching Required
Figure 203.05.G details the bench into the existing embankment. For side hill fills, the existing embankment is physically notched out and connected to the new embankment. Benching requires horizontal cuts in the existing slope.
The bench is wide enough to blend the new embankment with the existing embankment. In Figure 203.05.H, the total width between point A and B must be the width of the dozer blade and the compaction equipment.
Figure 203.05.H - Benching in New Embankment
If the plan calls for a new embankment, or the distance between C and B is less than a blade width or about 8 feet, then the existing embankment must be benched in the difference or distance A and C.
In Figure 203.05.I, the horizontal distance between points D and E is about 4 feet (1.3m). Therefore, the existing embankment must be benched into for about 4 more feet (1.3m) to complete the bench.
Figure 203.05.I - Sliver Fills
Bench into the slope as the embankment is placed, and compact into layers. Begin each bench at the intersection of the existing slope and the vertical cut of the previous bench. The re-compaction of the cut materials is required.
Benching is nothing more than a side hill foundation. Benching knits two embankments together to ensure that a failure plane does not occur. Figure 203.05.J details typical benching seen on some plans.
Figure 203.05.J - Typical Benching
In this case, the designer anticipated that there was a stability problem or weak soils in the existing embankment (or both). This is called special benching.
Side hill embankments present unique problems in that they may be stable when originally constructed yet become unstable later. The result is usually a landslide.
If the bench is not benched into the existing embankment far enough then a weak plane can develop as shown in Figure 203.05.K. A failure may occur along this weak plane and the bench material will move laterally. The project should evaluate the existing soil conditions and determine if more benching is required than shown on the plans or required by the specifications.
Figure 203.05.K - Benching Problems
In most cases, the main cause of embankment benching failure is by water seeping into the embankment from the side hill or foundation. Notice in Figure 203.05.K how water can move into the bench material and weaken the bench material.
Special attention must be given to side hill embankments. Consult the plans and soil profile to see where special benching, if any, is required; to see whether or not spring drains are provided, and to see if any potential spring or wet zones are mentioned. The areas should be inspected in detail for possible springs. In dry seasons, green or lush vegetation are often indicative of a semi-dormant spring that may become active during prolonged periods of precipitation. If spring zones are encountered and no spring drains are provided in the plans, then drains should be added to the work.
Spring drains are detailed on the plans by plan note D 109. It can be found at the following link:
http://www.dot.state.oh.us/cadd/notes/drainage.not
More detail can be found on Standard Drawing DM 1.1 on the second sheet. It can be found at the following link:
http://www.dot.state.oh.us/se/standard/Hydraulic/revisions/dm/pdf/dm11_07-19-02.pdf
The standard drawing is partially shown in figure 203.05.L. Use non-perforated pipe.
See Figure 203.05.M when more severe water problems are encountered. If the water is coming in at all elevations, then a filter fabric and number 8 aggregate can be placed to take the water flows. The fabric is used to stop the migration of fines into the number 8’s.
Figure 203.05.M - Severe Water Problems in a Bench
Figure 203.05.N - Typical Plan View with Bench Drainage
Figure 203.05.O - Typical Plan View with Water in the Bench
This section covers a general description of spreading and compacting materials. A more detailed explanation can be found in Section 1015 “Compaction Testing of Unbound Materails”.
The procedures outlined in this section will make or break the quality of the earthwork construction. Control over the lift thickness and compaction of the materials is vital to the success of the project.
Certain materials require compaction at thinner lifts than others to obtain their maximum strength. Other materials can be compacted in thicker lifts without sacrificing quality. Some materials require the addition of water to help in the compaction effort or to help break down the material, while other materials require mixing to get the desired results.
All embankment materials, except for rock in 203.06.C. and RPCC in 203.06.D, are spread in horizontal loose lifts not exceeding 8 inches (200 mm). All embankment material lifts, except for rock and hard shale, are compacted to a specified density and moisture requirements in 203.07.
The material is spread using dump trucks, scrapers, and dozers. In general, a sheepsfoot or tamping foot roller is used to compact rock, shale, clay, and silt material. Granular materials are generally compacted using a smooth drum vibratory roller.
The four methods used for compaction acceptance are proctor testing, test section method, aggregate correction method, and roller pass method.
Use a maximum lift thickness of 8 inches (200mm) for soil and granular embankment. Soil compaction acceptance is based on the proctor testing, test section method, or aggregate correction method. Granular material compaction acceptance is based on the test section method.
These methods are covered in the “Compaction Testing of Unbound Materials” Section 1015 of this manual.
Shale is consolidated mud. Shale may seem hard but in many instances it can be broken down to soil size with very little effort. See 203.02.P and 703.16.D in this manual for a full description of the material.
Some hard durable shales can be excavated or blasted in very large sizes. The Contractor controls the size of the material by the way they blast the material. During the typical rock blasting operation, the bench height/burden (L/B) ratio is greater than one, the production hole spacing (S) is 10 to 15 feet (3.3 to 5m), and the production hole diameter (D) is 6 inches (150mm). These dimensions are typical in order to maximize production. In addition, it generally leaves large chunks of rock or shale. These large pieces are fine for rock fills but are not conducive to shale fills
To produce smaller shale or rock fragmentation, the blaster can increase the L/B to about 3, decrease S to 6 to 8 feet, and reduce the D to about 4 inches (100mm). These dimensions are changed in a trial and error method. The most efficient method depends on the shale and rock formations.
If the Contractor does not control the material size during the excavation or blasting, then the amount of spreading, manipulation, compacting and watering will be extensive to get the material in 8-inch (200mm) lifts.
All shale material is placed and compacted in 8-inch (200mm) lifts. If the material is placed and compacted in thicker lifts then a situation such as in Figure 203.06.A can happen. Loose and non-durable shale intermixed within the lift can deteriorate later when water runs though the system.
Figure 203.06.A - Thick Lift of Shale
In many cases, when thick lifts are used, the compaction in the top 8 inches (200mm) may pass. If the top 8 inches (200mm) is removed, the lower material is made of loose and large chunks of soft shale.
Figure 203.06.C details what happens when shale is not properly placed and broken down. The embankment load on the shale along with the water going through the embankment causes the soft shale to break down.
Figure 203.06.C - Inadequate Shale Compaction and Breakdown
In order to ensure long-term durability, the project needs to determine how far to break the shale down in the field. The amount of breakage during construction is directly related to the durability and hardness of the shale. The hardness and durability are correlated to the bucket test and roller pass methods in the specifications.
The specifications require that the shale be tested for compaction and broken down according to the bucket test and the subsequent roller pass evaluation.
A summary of this evaluation follows:
If % retained on 3/4 inch sieve is… |
Then… |
less than 25 |
|
25 to 75 |
An even percentage of soil, small-, and coarse-sized shale is obtained (maximum contact with all particles). Shale should have a granular texture when properly broken down in the field (see Figure 203.06.B). |
greater than 75 |
Field test for hardness (703.16.D) |
If % that breaks down is… |
Then… |
greater than 40 |
Break material can into a granular texture as detailed in Figure 203.06.B |
40 or less |
Use the procedure in section 203.06.B in CMS (Hard Durable Shale): 10 passes with a 15-ton roller, and fill the voids |
Figure 203.06.B - Granular Texture Shale
The above procedure is a systematic approach to evaluating potential shale breakage in the field. In practice, field results will vary because of variability of shale and the mixing of different types of shale and rock. Some judgment is required by the project during construction.
The most important factors in the long-term quality of shale fills are:
The rock fill requirements have slightly changed from the previous versions.
i. Whichever results in the smaller lift.
i. Within a length of 6x the height of the fill at the abutment.
ii. Use less than 18 inches (0.5 m) lifts.
iii. Example:
1. Fill height is 20 feet (6 m),
2. 20 x 6 = 120 feet (36 m).
The rock fill construction is outlined below:
When using other embankment materials with rock, use rock as:
Use other embankment material as follows:
i. Better drainage
When the rock fill contains more than 15 % shale, then compact like a shale fill.
Random materials are a wide variety of materials which do not fit any other groupings. They may be rock mixed with soil, brick, asphalt mixed with soil, or portland cement concrete mixed with soil.
Soil mixed with any other random material must be at least 2 % below optimum. This will help fill the voids and create a stable embankment.
Recycled asphalt or concrete are mixed with at least 30 % natural materials.
Random material mixtures are placed in 8-inch lifts, except for RPCC:
Except for rock and hard shale the moisture and density controls in this section apply. The Department will perform all compaction tests according to Supplement 1015. This supplement is detailed in Section 1015 “Compaction Testing of Unbound Materials” of this manual.
Water is added or subtracted to a condition to obtain the density and stability. Dry or add moisture throughout the lift. Expedite and manipulate the material by using plows or discs. Soils with pronounced elasticity or deformation reduce the moisture content to secure stability.
In a fill situation without a soft foundation, heavy equipment may deflect the soil but no permanent rutting or cracking should be evident afterwards.
Some soils require moisture contents 5% below optimum to secure stability. Materials such as A-4a, A-4b, and A6a’s are notorious for this problem. These materials are difficult to compact during marginal weather conditions and just after a rainy day.
The elasticity may be caused by foundation conditions. See Materials 203.02, “Elasticity and Deformation of Soils” in this manual.
Do not mix shale in the lifts to reduce the moisture content. The shale will bring the moisture down then break down later causing settlement or a landslide.
Table 203.07-1 details the “EMBANKMENT COMPACTION REQUIREMENTS”. The percentage is based on the maximum dry weight of the soil. This table is used for materials tested using proctor testing or aggregate correction testing methods.
Dry Weight (lb/ft3) |
Percent |
90 to 104.9 |
102 |
105 to 119.9 |
100 |
120 and more |
98 |
Table 203.07-1 – Embankment Compaction Requirements
Test sections are required for granular materials and other materials. If test section results are used then the following apply:
More detail is in Supplement 1015 “Compaction Testing of Unbound Materials” in this manual.
This section of the manual is intended to give a brief outline of some of the methods to determine earthwork quantities. Methods described in this section are acceptable for making this check.
The specifications require that the average-end-area method be used to determine volumes of earthwork for payment.
There are many acceptable methods for determining end areas for earthwork computations. Any method that gives accurate determinations may be used. Some of the most common methods for determining cross section end areas are as follows:
In this method, an instrument with a wheel and a graduated dial is run around the perimeter of a cross sectional end area. The area is found by multiplying the reading on the dial by a constant factor or by setting a factor on the planimeter and by reading the area directly from the planimeter dial.
In this method, the number of unit squares in a section is counted. This is not practical except for very small sections.
This is a method of tallying unit squares by making successive marks on a strip of paper to measure unit strips, accumulating all unit strips on a cross section, and converting to total cross section area. This method is simple and rapid and keeps the chance of error to a minimum.
In this method, data from cross sections (usually in coordinate form) is input into a computer program, which follows a program setup to finish areas and volumes.
Most plans are developed using computer aided design (CAD) programs. In these files, the earthwork calculations are detailed. Contact Production for these calculations.
In this method, the section is broken into areas, such as triangles and trapezoids. Each area is then calculated by its geometry. The total area is found by summing the individual areas.
This method calculates end area using a formula. Data for the formula is taken from a cross section (or field notes) showing elevation and distance from a base line for each break in the cross section line. A pocket calculator can be used for this calculation.
Determination of cross section end areas by this method is exact and any two persons using the same information (field notes) will obtain the same answer, providing no errors are made in the calculator manipulation or arithmetic calculations. There is only one correct answer.
The two methods are described and illustrated in Figures 203.09.A-D.
Figure 203.09.A - End Area Determination Method 1
Figure 203.09.B - End Area Determination Method 1 (Metric)
Figure 203.09.C - End Area Determination Method 2
Figure 203.09.D - End Area Determination Method 2 (Metric)
The end areas of English plans are detailed in square feet (ft2), while end areas on metric plans are detailed in square meters (m2). Make the appropriate volume calculation shown below using the end area found in Figures 203.09.A-D.
For base lines and center lines on tangent, and for center lines on curves where the center line of the curve coincides with the center of mass (centroid) of the cross sections, the formula for computing volume from end areas are as follows:
|
where
V = volume in cubic yards (yd3)
A = cross section one end area in square feet (ft2)
A1 = cross section of other end area in square feet (ft2)
L = distance between A and A1 in feet (ft)
|
where
V = volume in cubic meters (m3)
A = cross section one end area in square meters (m2)
A1 = cross section of other end area in square meters (m2)
L = distance between A and A1 in meters (m)
Figure 203.09.E shows a table for use in determining cubic yards (yd3) from the sum of end areas for sections 100 ft. apart, and for conditions described above. This table cannot be used on metric projects.
Figure 203.09.E - Cubic Yards for the Sum of the End Areas
Figure 203.09.F Earthwork Calculations depicts a form that can be used to summarize the earthwork calculations.
Figure 203.09.F - Earthwork Quantity Calculations Form
Figure 203.09.G shows a completed calculation form.
Figure 203.09.G - Completed Earthwork Quantity Calculations Form
Where cross sections are at right angles to curve center lines, and the center line is not located at the center of mass (centroid) of the cross sections, corrections must be applied to volume calculations to obtain an accurate result. This is especially true for curves of short radius, such as those commonly used on ramps. Inaccuracies of considerable magnitude may result unless proper corrections have been used in calculating earthwork volumes. General methods for determining accurate quantities in such cases are detailed in Section 1310.3.2 and further detailed in Figure 1310-1 Productions Volume 3 Design Manual
The details may be found at the following link
http://www.dot.state.oh.us/prod/volume3/1300/CHAP1300.PDF
In the 2002 specifications, all of the statements that referred to payment were transferred to this section. There are a multitude of statements that denote when the Department will and will not pay for earthwork quantities based on different field circumstances.
The project should review this section. In this manual, we will focus on the final quantity measurements.
The electronic methods are not detailed in section 203.09 or 203.10 of this manual. Electronic devices connected to graders or dozers are allowed in Item 623 in section 623.02 on page 581 in CMS.
The specifications on these matters need to be changed in the future. When the specifications are changed then this manual will be updated.
Check measurements are made in areas where earthwork is being performed. A sufficient number of these checks must be recorded according to the instructions in this manual to provide a satisfactory record of the checks. The purpose of these measurements and records are:
This will result in the savings of engineering man-hours required to arrive at payment quantities and make it possible for the Contractor to receive prompt final payment after the completion of the work.
Final cross sections of roadway earthwork are usually not required provided that the plan quantities are checked for accuracy and adequate checks have been made (and recorded) during construction. This establishes that plan quantities of earthwork have been performed within specified tolerances.
However, final cross sections may be called for by the Office of Construction where, by inspection or other knowledge of the project, it is indicated that measurement by final cross section is necessary or desirable.
i. Total contract changes greater than $5000.
ii. Two consecutive end areas varying by more than 5 percent.
iii. Undercutting.
iv. Foundation settlement.
v. Changes in the grades or slopes.
vi. Removing slides.
vii. Arithmetic errors.
Specifying borrow under the 2002 specifications occurs in rare cases and only when the measurement in the final location is impractical. An example would be underwater or linear grading operations. Borrow will be specified by weight, when practical.
Volume Measurement
When borrow is specified by the cubic yard, measurement may be taken in the borrow pit just as in regular embankment construction. Use the average end areas.
Only use Department personnel to make all measurements of the borrow. Contractor's employees may be used to assist in check measurements and measurements of authorized excavations beyond plan lines where the quantity at each location is less than 2,000 cubic yards (yd3) [1500 cubic meters (m3)]. This assumes that project personnel only are responsible for collecting, plotting, and calculating of the data and quantities.
Weight Measurement
When borrow is specified by cubic yard, weight measurements may be used to calculate the payment:
|
This can be used as a check or if cross-sections were not available.
Volume Measurement
|
Equation
203.11 – Calculation of Payment from Weights (Other than Natural Formation) |
Weight tickets minus excess moisture.
Collect weight tickets according to 109.01.
The quantity of borrow for payment is the measured as detailed above minus:
|
i. Borrow was measured at the borrow site.
ii. A larger amount of borrow fit into the embankment.
1. Density is greater at the embankment location.
iii. Therefore, we subtract less borrow from the final pay.
Record all check measurements and check calculations on an appropriate form, date and sign or initial the form, and place it in the project records.
Records of check measurements must be kept up-to-date at the project office during construction and will be reviewed by the Office of Construction during their routine visits to the project.
After completion of the earthwork, prepare a tabulation of earthwork pay items showing plan quantities where applicable, and listing appropriate measured quantities for all areas where there was deviation from plan lines beyond specified tolerances which affect the pay quantities, showing total quantities for payment.
This tabulation, together with records of check measurements, constitutes the earthwork report for the project. After processing, these reports shall be filed in the District Office.