ITEM
623 CONSTRUCTION LAYOUT STAKES
and Survey Monuments
623.01
Description
623.02 Materials
623.03 Definitions
623.04
Verification
623.05 Placement,
Protection and Restoration of Survey Monuments
623.06 Primary
Project Control
623.07 Right-of-Way
Staking
623.08 Construction
Layout Staking
623.09 Providing
Electronic Instrumentation
623.10 Method
of Measurement
623.11 Basis of
Payment
623.01
Description.
This work consists of furnishing, placing, and maintaining construction layout
stakes necessary to perform the Work under the Contract. This work also
includes verification, placement, protection, and necessary restoration of
primary project control monuments, monument assemblies, reference monuments
(which include centerline monuments and centerline reference monuments), and
Right-of-Way monuments.
Ensure
that all work associated with locating and setting reference monuments,
Right-of-Way monuments, and steel rods in monument assemblies is performed by a
Registered Surveyor. Ensure that all other surveying and layout work
described below is supervised by a Registered Engineer or a Registered
Surveyor.
623.02
Materials.
Furnish materials conforming to:
Concrete, Class QC Misc or QC 1............................... 499
Cast frames and
covers.............. 711.12, 711.13, or 711.14
Concrete sand (fine
aggregate)............................. 703.02.A
Stainless steel
bolts.................................................. 730.10
Steel
rods................................................................. 709.01
Pipe...........................................
706.07, 706.09,
or 707.45
A. Survey Monuments. Includes primary project
control monuments (including azimuth marks and temporary benchmarks), monument assemblies,
centerline monuments, centerline reference monuments, and Right-of-Way
monuments.
B. Primary Project
Control Monument. A surveyed position that is established and
constructed according to the Department’s Survey
and Mapping Specifications. Primary project control monuments
will have associated azimuth marks and may have associated temporary
benchmarks.
C. Monument Assembly. A surveyed position typically set inside
pavement that consists of a steel rod housed inside a monument assembly box
with a cast frame and cover according to
SCD RM‑1.1.
1.
Centerline Monument. A surveyed position outside of pavement that
consists of a steel rod and aluminum cap encased in concrete according to SCD
RM-1.1 that defines the centerline.
2.
Centerline Reference Monument. A surveyed position outside of pavement that consists
of a steel rod and aluminum cap encased in concrete according to SCD
RM-1.1, that defines the centerline based on a specific offset from that
centerline.
E. Right-of-Way Monument. A
property boundary monument set according to SCD
RM-1.1 to comply with Ohio
Administrative Code Section 4733-37, “Standards for Boundary Surveys in the
State of Ohio” and recited in the Right-of-Way deeds to convey the property or
easement rights. Right-of-Way monuments are set at property corners,
property line intersections, points along the Right-of-Way and angle points on
the Right-of-Way.
F. Azimuth Mark. A project control monument set at the end
points of the project for use as a “backsight” point.
G. Temporary Benchmark. A vertical position transferred from a primary
project control monument.
623.04 Verification. Verify the position of
all survey monuments shown in the Contract Documents prior to construction
activities. Use standard acceptable surveying measurement techniques
suitable to meet the requirements of Ohio
Administrative Code Section 4733-37, “Standards for Boundary
Surveys”. Have a Registered Surveyor prepare a verification report with
the coordinates, station, offset, and a description of each survey monument
found before beginning earth moving, resurfacing, or paving activities.
Include the size, material, condition, any cap stamping or markings, and note
any differences from the plan locations of the survey monuments. Have the
Registered Surveyor sign and seal the verification report and submit it to the
Engineer and the District Survey Operations Manager. If additional survey
monuments not shown in the Contract Documents are encountered, protect,
reference, and preserve them in the same manner as survey monuments that are
shown in the Contract Documents. Include the additional survey monuments
in the verification report.
623.05
Placement, Protection and Restoration of Survey Monuments. When
specified in the Contract Documents, locate, construct, and position primary
project control monuments according to the Department’s Survey
and Mapping Specifications. Construct all other survey monuments
according to SCD
RM-1.1.
Do
not disturb survey monuments, cornerstones, or boundary monuments during
construction unless specified in the Contract Documents. Restore survey
monuments damaged or destroyed by construction activities, unless directed
otherwise by the Engineer.
Have
a Registered Surveyor prepare a report and drawing with the coordinates,
station, offset, and description of each survey monument that is constructed or
restored. Have the Registered Surveyor sign and seal the verification
report and submit it to the Engineer and the District Survey Operations
Manager.
If
the Department must repair, replace, or resurvey the location of any survey
monuments, cornerstones, or boundary monuments that are damaged, destroyed, or
made inaccessible by the Contractor or its employees, subcontractors, or their
agents, then the Engineer will deduct the costs incurred by the Department from
the estimates to the Contractor.
623.06
Primary Project Control. Primary project control governs all
positioning for Department projects. Use project control information
provided in the plans for all project related survey operations.
Establish and construct primary project control monuments according to the Department’s
Survey
and Mapping Specifications.
623.07
Right-of-Way Staking. Stake Right-of-Way lines where work will be
performed before beginning the work. Stake Right-of-Way lines by placing
tall stakes, properly identified and readily discernible, at points of change
in width or direction of the Right-of-Way line and at points along the line so
that at least two stakes can be seen distinctly from any point on the
line. The Engineer will not require the Contractor to set additional
stakes to locate a utility line that is not included as a pay item in the
contract, or to determine the property line between properties.
623.08
Construction Layout Staking. Furnish construction layout
staking as required to construct the project and along both sides of the
centerline of construction, 3 feet (1 m) outside of the grading limits at
maximum spacing intervals shown in the table below. Replace staking as
directed by the Engineer.
Table
623.09-1
Maximum Spacing of Construction Layout Stakes
Length of project |
Spacing |
|
Length of project |
Spacing |
Less than 1/2 mile |
200 feet |
|
Less than 1 km |
50 m |
1/2 mile to 1 mile |
500 feet |
|
1 km to 2 km |
200 m |
Over 1 mile |
1000 feet |
|
Over 2 km |
500 m |
Before
performing a portion of the Work, submit a copy of the construction layout
notes for that portion to the Engineer. The construction layout notes must
contain information sufficient for the Engineer to verify the construction
layout.
The
Contractor is responsible for having the finished Work conform to the lines,
grades, elevations and dimensions shown on the plans. Any inspection or
checking of the Contractor’s layout by the Engineer and the acceptance of all
or any part of it does not relieve the Contractor of that responsibility.
The
removal of construction layout stakes at the completion of the Work is a final
cleanup item that is required as a condition of full payment for Item 624 Mobilization.
623.09
Providing Electronic Instrumentation. If specified as a pay item,
provide the Engineer with electronic instrumentation so that the Department can
verify the construction layout, perform check sections, and document pay
items. Provide a survey-grade, global navigation satellite system (GNSS) receiver and data collector. Provide equipment
that meets the requirements of the Department’s Survey
and Mapping Specifications.
Provide
equipment, software, and all three dimensional models needed to verify layout,
perform check sections, and document pay items. Train the Engineer on how
to use the provided equipment and software and provide technical assistance
during the duration of the Work.
Upon
completion of the Work, the electronic equipment, computer and software will
remain the property of the Contractor.
If
using GNSS methods to construct the project and a pay
item for providing electronic instrumentation is not specified, provide the
Engineer with the three dimensional models in electronic format when
requested. Provide the models at no additional expense to the Department.
623.10 Method of Measurement.
Estimated quantities for replacement of Primary Project Control Monuments,
Monument Assemblies, Reference Monuments, and Right-of-Way Monuments expected
to be destroyed that are within the project construction work limits are
included in the Contract Documents. Estimated quantities for new
monuments are also included in the Contract Documents.
Primary
project control monuments, monument assemblies, reference monuments,
Right-of-Way monuments, and boundary monuments on or outside the project
construction work limits are the Contractor’s responsibility to protect and
restore as required. The Department will not pay for restoration of these
items.
623.11
Basis of Payment.
Payment for Construction Layout Stakes and Surveying includes payment for
Right-of-Way staking and verifying the location of existing survey monuments.
The Department will consider the cost for locating new survey monuments to be
included in the unit price bid for the survey monument. The Department will
pay for accepted quantities at the contract prices as follows:
Item
Unit
Description
623
Lump
Sum
Construction Layout Stakes and Surveying
623
Lump
Sum
Providing Electronic Instrumentation
623
Each
Primary Project Control Monument, Type A
623
Each
Primary Project Control Monument, Type B
623
Each
Monument Assembly
623
Each
Reference Monument
623
Each
Right-of-Way Monument