Lebanon (Friday, May 9, 2014) – Work the week of May 12 on the I-75/Hopple Street interchange construction will require the following closures:

 

·         Two right lanes of southbound I-75 from 10 p.m. to 6 a.m. Monday, May 12 through Friday, May 16. Also, the ramp from southbound I-75 to Hopple Street will be closed each night from 10 p.m. to 5 a.m.

·         Northbound I-75 ramp to Hopple Street closure from 3 a.m. to 5 a.m. Monday, May 12.

·         30-minute closures of Central Parkway between 10 p.m. to 5 a.m. each day.

·         Lane closures on Marshall Avenue from 9 a.m. to 3 p.m. each day.

·         Right lane closure on northbound Central Parkway from 9 a.m. to 3 p.m. each day.

·         Closures on various side streets from 9 a.m. to 3 p.m. each day.

 