Full closure of I-75 rescheduled for Dec. 8 and Dec. 10

Hamilton County (Friday, Dec. 5, 2014) – The full closure of southbound I-75 between the SR 562 and Mitchell Avenue interchanges originally scheduled for this weekend will now take place Monday, Dec. 8 and Wednesday, Dec. 10.

Closures for the railroad bridge replacement project are as follows:

Saturday, Dec. 6 - Closure of SR 562 ramp to southbound I-75 and single lane closure on southbound I-75 at 7 p.m., followed by double lane closure at 10 p.m., with all lanes reopened to traffic by 6 a.m. Sunday, Dec. 7

Monday, Dec. 8 - Closure of SR 562 ramp to southbound I-75 at 9 p.m., followed by full closure of southbound I-75 at 11 p.m. with all lanes reopened to traffic by 6 a.m. Tuesday, Dec. 9. Suggested detour is west on I-275 to east on I-74 to I-75. The ramp from southbound I-75 to eastbound SR 562 will be open to traffic as well.

Tuesday, Dec. 9 - Closure of SR 562 ramp to southbound I-75 at 9 p.m.; single lane closure on southbound I-75 at 8 p.m., followed by double lane closure at 11 p.m., with all lanes reopened to traffic by 6 a.m. Wednesday, Dec. 10

Wednesday, Dec. 10 - Closure of SR 562 ramp to southbound I-75 at 9 p.m., followed by full closure of southbound I-75 at 11 p.m. with all lanes reopened to traffic by 6 a.m. Thursday, Dec. 11. Suggested detour is west on I-275 to east on I-74 to I-75. The ramp from southbound I-75 to eastbound SR 562 will be open to traffic as well.

Thursday, Dec. 11 - Closure of SR 562 ramp to southbound I-75 at 9 p.m.; single lane closure on southbound I-75 at 8 p.m., followed by double lane closure at 11 p.m., with all lanes reopened to traffic by 6 a.m. Friday, Dec. 12. Also, a rolling road block will be in place on southbound I-7.

Friday, Dec. 12 - Closure of SR 562 ramp to southbound I-75 at 9 p.m.; single lane closure on north and southbound I-75 at 8 p.m., followed by double lane closure on southbound I-75 at 11 p.m., with all lanes reopened to traffic by 6 a.m. Saturday, Dec. 13.

All work is dependent on the weather. Traffic will be maintained with law enforcement officers, and arrow boards and signs will be in place to alert motorists of the upcoming closure and detour. To help ensure the safety of the construction workers as well as the traveling public, motorists should remain alert, reduce their speed and watch for stopped traffic while passing through the work zone.​