– Work the week of May 12 on the I-75/Hopple Street interchange construction
will require the following closures:
·
Two
right lanes of southbound I-75 from 10 p.m. to 6 a.m. Monday, May 12 through
Friday, May 16. Also, the ramp from southbound I-75 to Hopple Street will be
closed each night from 10 p.m. to 5 a.m.
·
Northbound
I-75 ramp to Hopple Street closure from 3 a.m. to 5 a.m. Monday, May 12.
·
30-minute
closures of Central Parkway between 10 p.m. to 5 a.m. each day.
·
Lane
closures on Marshall Avenue from 9 a.m. to 3 p.m. each day.
·
Right
lane closure on northbound Central Parkway from 9 a.m. to 3 p.m. each day.
·
Closures
on various side streets from 9 a.m. to 3 p.m. each day.
All work
is weather permitting.