I-75/Hopple Street construction update

I-75/Hopple construction update week of April 13

Hamilton County (Monday, April 13, 2015) – Ongoing work to reconstruct the Interstate 75 at Hopple Street interchange requires  the following closures this week:

Right lane of eastbound I-74 from Colerain Avenue to Hopple Street bridge, 8 p.m. Tuesday, April 14.

Right lane of northbound I-75 from Hopple Street to the I-74 ramp, 8 p.m. Tuesday, April 14. 

Right lane of southbound I-75 from the Monmouth Street bridge to the Hopple Street bridge,8 p.m. Wednesday, April 15. Ramp from southbound I-75 to Hopple Street, 10 p.m. Wednesday, April 15.

Ramp from Hopple Street to southbound I-75, 10 p.m. Wednesday, April 15.

Left lane of eastbound I-74 from the Central Parkway/I-75 split to the I-75/I-74 merge, 8 p.m. Thursday, April 16.  

Right lane of southbound I-75 from the I-74 exit to the I-75/I-74 merge, 8 p.m. Thursday, April 16.

Right lanes of north and southbound I-75, 8 p.m. Thursday, April 16.

Ramp from southbound I-75 to Harrison Avenue, 10 p.m. Thursday April 16.

All lanes and ramps are to reopen to traffic by 6 a.m. the following day.

Various side street flagging operations for material deliveries and equipment relocation 9 a.m. to 3 p.m. daily.        

 Arrow boards and/or signs will be in place to alert motorists of the upcoming ramp and lane closures. All work is dependent upon weather.

To help ensure the safety of the construction workers as well as the traveling public, motorists should remain alert, reduce their speed and watch for stopped traffic while passing through the work zone.