Ohio.gov State Agencies  |  Online Services
Skip Ribbon Commands
Skip to main content
  
  
RouteSection
  
  
  
  
  
collapse LetDate : 12/12/2014 ‎(1)
14201196284
TEST LAB RENOVATION
12MISCELLANEOUS142011
collapse LetDate : 12/11/2014 ‎(21)
14053576938
US 33-05.60(Carroll Area)
5NEW CONSTRUCTION140535
1
14053676032
IR 75-6.70
2MAJOR WIDENING140536
14057386586
41-0.89
9CULVERT REPLACEMENT140573
14057488982
US 68-31.28
9TWO LANE RESURFACING140574
14057522891
IR 77-13.75
12BRIDGE REPLACEMENT (1 BRIDGE)140575
14057687326
BH-FY 2015
9BRIDGE REPAIR140576
14057797865
IR 77-VAR/KNO-US 62-22.30
5SLIDE REPAIR140577
14057882832
SR 56-13.60
10TWO LANE RESURFACING140578
14057996952
SR 2-11.50
12NOISE WALLS140579
14058092877
Toland Street Bridge
6BRIDGE REPLACEMENT (1 BRIDGE)140580
14058196567
SR 94-14.61 (I-271 Ramp)
3SIGNALIZATION140581
14058277240
CR 146-0.28
6BRIDGE REPLACEMENT (1 BRIDGE)140582
14058390435
SR 821-4.88
10CULVERT REPLACEMENT140583
14058488766
SR 65-7.57/8.63
7BRIDGE REPLACEMENT (1 BRIDGE)140584
14058593643
SR 327-6.89
10TWO LANE RESURFACING140585
14058683453
BH-FY2015
3BRIDGE PAINTING140586
14058792375
SR 65-5.89 Resurf
2TWO LANE RESURFACING140587
14058891802
SR 41/SR 55-9.46/8.21/11.62
7TWO LANE RESURFACING140588
14058994037
Shawnee Culvert Project #1
9CULVERT REPLACEMENT140589
14109487099
/PRE-GCS-FY2015
8CRACK SEALING141094
14109587612
MOW-FY2015/2016
5MOWING141095
collapse LetDate : 11/26/2014 ‎(17)
14055675625
Bridge Maintenance FY2015
8BRIDGE REPAIR140556
14055788764
US 6-11.25
3TWO LANE RESURFACING140557
14055890649
SR 3-24.47
6MISCELLANEOUS140558
14055992740
SR 141-17.00
10SLIDE REPAIR140559
14056082972
IR 275-16.19
8FOUR LANE RESURFACING140560
14056191715
SR 56-5.38
10BRIDGE REPLACEMENT (1 BRIDGE)140561
14056285113
SR 43-5.58
11TWO LANE RESURFACING140562
14056388767
SR 511-13.41
3TWO LANE RESURFACING140563
14056482262
US 20-8.56, LOR-SR 10C-0.73, LOR-SR 10-6.52
3SIGNING140564
14056593113
SR 57-03.24
3TWO LANE RESURFACING140565
14056693779
SR 721-05.21
7BRIDGE REPAIR140566
14056791431
SR 7-15.07
10PREVENTIVE MAINTENANCE140567
14056888951
US 22-07.63/12.02
5BRIDGE REPAIR140568
14056987745
US 30-9.18
3PREVENTIVE MAINTENANCE140569
14057092353
SR 149-8.28
11SLIDE REPAIR140570
14057189400
SR 327-19.44 Rockfall Repair
9SLIDE REPAIR140571
14057283652
SR 772-13.50 Slide/Culvert
9SLIDE REPAIR140572
collapse LetDate : 11/13/2014 ‎(21)
14053783599
US 20-21.43
4BRIDGE REPLACEMENT (1 BRIDGE)140537
14053884610
-SR 28-8.52
8BRIDGE REPLACEMENT (1 BRIDGE)140538
1
14053993108
SR 98-19.30
3TWO LANE RESURFACING140539
14054084489
IR 71-12.45
12BRIDGE REPAIR140540
14054191145
GR-FY2015
10GUARDRAIL REBUILDING140541
14054287262
-SR 37-(4.53)(22.13)
6BRIDGE REPAIR140542
1
14054384556
-US 250-01.14
3INTERSECTION140543
1
14054494898
US 250-9.78
3CULVERT REPLACEMENT140544
14054576433
-IR 70-00.00
5FOUR LANE RESURFACING140545
2
14054688985
SR 138-22.89
9TWO LANE RESURFACING140546
14054793987
SR 7-28.10
11BRIDGE REPLACEMENT (1 BRIDGE)140547
14054893116
SR 301-00.00
3TWO LANE RESURFACING140548
14054987534
IR 75-12.90/13.15/13.28
7BRIDGE REPAIR140549
14055092851
-SR 348-6.97
9SLIDE REPAIR140550
1
14055191862
SR 47-14.51
7TWO LANE RESURFACING140551
14055290399
IR 77-20.54
11SIGNING140552
14055396093
SR 47-13.55
6TWO LANE RESURFACING140553
14055493864
Mohican SP Campground
3TWO LANE RESURFACING140554
14055593869
IR 80-2.20
4SIGNALIZATION140555
14302077572
SR 665-3.95
6BRIDGE REPLACEMENT (1 BRIDGE)143020
14302122523
SR 7-10.12
10FOUR LANE RESURFACING143021
collapse LetDate : 11/6/2014 ‎(4)
14048577254
-75-4.52 Ph 2 (PART 1, PART 2, PART 3)
2MAJOR RECONSTRUCTION140485
7
14052190246
US 40-21.35
6BRIDGE REPLACEMENT (1 BRIDGE)140521
5
14052276282
US 40-4.69
6MAJOR WIDENING140522
4
14700298920
US 35-17.68
10BRIDGE REPAIR147002